Identify the critical path for the following three scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a 'Website': Activity Description Duration (weeks) Preceding Activities A Determine user needs 3 B Review s/w and languages 1 C Purchase software 4 D Design format and style 4 B E Write programs 2 A F Review outcome product with user 5 C G Make revisions 1 D, F H Select server site 3 E I Install on server and test 6 G J 3 H, I 1. Draw the path. 2. Calculate the early finishing time (forwards calculations) 3. Highlight the total time to complete the project (weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
Identify the critical path for the following three scenarios of a project activities (tables given
below) and their required times to be completed in addition to their predecessors for developing
a Website':
Activity
Description
Duration (weeks)
Preceding Activities
A
Determine user needs
3
Review s/w and languages
1
C
Purchase software
4
D
Design format and style
4
B
E
Write programs
A
F
Review outcome product with user
C
G
Make revisions
1
D, F
H
Select server site
3
E
I
Install on server and test
6.
G
J
3
Н, I
1. Draw the path.
2. Calculate the early finishing time (forwards calculations)
3. Highlight the total time to complete the project (weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
Transcribed Image Text:Identify the critical path for the following three scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website': Activity Description Duration (weeks) Preceding Activities A Determine user needs 3 Review s/w and languages 1 C Purchase software 4 D Design format and style 4 B E Write programs A F Review outcome product with user C G Make revisions 1 D, F H Select server site 3 E I Install on server and test 6. G J 3 Н, I 1. Draw the path. 2. Calculate the early finishing time (forwards calculations) 3. Highlight the total time to complete the project (weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities)
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.