I need help with part a b and c in question 2. Question one is listed because it is referenced in question 2. Any help with question 2 would be appreciated even if it is not all 3 parts. thank you 1. A certain batch of parts is routed through six machines in a batch production plant. The setup and operation times for each machine are given in the table below. Batch size is 200 and the average nonoperation time per machine is15 hr. Determine (a) manufacturing lead time and (b) hourly production rate for operation 4.Machine 1 2 3 4 5 6Setup time (hr) 5 3 6 4 5 3Operation time (min) 3.0 3.3 8.2 3.9 4.5 2.3 a. 6(4.3+200(3.9/60)+15) = 193.8 hours 24.2 days if 8 hour shiftb. 4(60)+200(3.9)/200 =5.1 hourly production for operation 4 2. Suppose the part in the previous problem is made in very large quantities on a production line in which an automated work handling system is used to transfer parts between machines. Transfer time between stations is 30 sec. total time required to setup the entire line is 102 hr. Assume that the operation times at the individual machines remain the same as in the previous problem, Determine (a) manufacturing lead time for a part coming off the line, (b) production rate for operation 3, (c) theoretical production rate for the entire production line, (d) How long would it take to produce 15,000 parts after the setup has been completed?
I need help with part a b and c in question 2. Question one is listed because it is referenced in question 2. Any help with question 2 would be appreciated even if it is not all 3 parts.
thank you
1. A certain batch of parts is routed through six machines in a batch production plant. The setup and operation times for each machine are given in the table below. Batch size is 200 and the average nonoperation time per machine is15 hr. Determine (a)
manufacturing lead time and (b) hourly production rate for operation 4.
Machine 1 2 3 4 5 6
Setup time (hr) 5 3 6 4 5 3
Operation time (min) 3.0 3.3 8.2 3.9 4.5 2.3
a. 6(4.3+200(3.9/60)+15) = 193.8 hours 24.2 days if 8 hour shift
b. 4(60)+200(3.9)/200 =5.1 hourly production for operation 4
2. Suppose the part in the previous problem is made in very large quantities on a production line in which an automated work handling system is used to transfer parts between machines. Transfer time between stations is 30 sec. total time required to setup the entire line is 102 hr. Assume that the operation times at the individual machines remain the same as in the previous problem, Determine (a) manufacturing lead time for a part coming off the line, (b) production rate for operation 3, (c) theoretical production rate for the entire production line, (d) How long would it take to produce 15,000 parts after the setup has been completed?
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Elements Of Electromagnetics](https://www.bartleby.com/isbn_cover_images/9780190698614/9780190698614_smallCoverImage.gif)
![Mechanics of Materials (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134319650/9780134319650_smallCoverImage.gif)
![Thermodynamics: An Engineering Approach](https://www.bartleby.com/isbn_cover_images/9781259822674/9781259822674_smallCoverImage.gif)
![Elements Of Electromagnetics](https://www.bartleby.com/isbn_cover_images/9780190698614/9780190698614_smallCoverImage.gif)
![Mechanics of Materials (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134319650/9780134319650_smallCoverImage.gif)
![Thermodynamics: An Engineering Approach](https://www.bartleby.com/isbn_cover_images/9781259822674/9781259822674_smallCoverImage.gif)
![Control Systems Engineering](https://www.bartleby.com/isbn_cover_images/9781118170519/9781118170519_smallCoverImage.gif)
![Mechanics of Materials (MindTap Course List)](https://www.bartleby.com/isbn_cover_images/9781337093347/9781337093347_smallCoverImage.gif)
![Engineering Mechanics: Statics](https://www.bartleby.com/isbn_cover_images/9781118807330/9781118807330_smallCoverImage.gif)