How much is the Gross Profit/Loss Realized in 2018? PAPASA Co. has consistently used the percentage of completion to account for its construction projects. On January 31, 2017, the company began work on a P4,500,000 construction contract. At the inception date, the estimated cost of the construction was P3,375,000. The following relates to the project Gross Profit- 2017 450,000 Cost incurred to date- 2018 2,700,000 Estimated cost to complete- 2018 900,000 Progress billings 2018 3,500,000
How much is the Gross Profit/Loss Realized in 2018? PAPASA Co. has consistently used the percentage of completion to account for its construction projects. On January 31, 2017, the company began work on a P4,500,000 construction contract. At the inception date, the estimated cost of the construction was P3,375,000. The following relates to the project Gross Profit- 2017 450,000 Cost incurred to date- 2018 2,700,000 Estimated cost to complete- 2018 900,000 Progress billings 2018 3,500,000
Chapter16: Accounting Periods And Methods
Section: Chapter Questions
Problem 40P
Related questions
Question
![How much is the Gross Profit/Loss Realized in 2018?
PAPASA Co. has consistently used the percentage of completion to account for its construction projects. On
January 31, 2017, the company began work on a P4,500,000 construction contract. At the inception date, the
estimated cost of the construction was P3,375,000. The following relates to the project
Gross Profit- 2017
450,000
Cost incurred to date- 2018
2,700,000
Estimated cost to complete- 2018
900,000
Progress billings 2018
3,500,000](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F1ffc59ab-753b-4631-88cf-f78ee5d208a5%2F53e6b4bd-064b-4478-983f-ae03796b0cc5%2Fqrkbqiu_processed.jpeg&w=3840&q=75)
Transcribed Image Text:How much is the Gross Profit/Loss Realized in 2018?
PAPASA Co. has consistently used the percentage of completion to account for its construction projects. On
January 31, 2017, the company began work on a P4,500,000 construction contract. At the inception date, the
estimated cost of the construction was P3,375,000. The following relates to the project
Gross Profit- 2017
450,000
Cost incurred to date- 2018
2,700,000
Estimated cost to complete- 2018
900,000
Progress billings 2018
3,500,000
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)