First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Job D was scheduled to begin early on day 2 and take 6.5 days. As of now (the review point after day 4), it is 2 days ahead of schedule. Job E should begin on day 1 and take 5 days. It was on time. Day Job 123456789 10 11 Job F was to begin on day 3, but maintenance forced a delay of 1.0 day. The job should now take 5 full days. It is now on schedule. D Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to complete. E Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks. F G Now LV

Holt Mcdougal Larson Pre-algebra: Student Edition 2012
1st Edition
ISBN:9780547587776
Author:HOLT MCDOUGAL
Publisher:HOLT MCDOUGAL
Chapter11: Data Analysis And Probability
Section11.1: Stem-and-leaf Plots And Histograms
Problem 10E
Question
First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are
reviewing the Gantt chart at the end of day 4.
Job D was scheduled to begin early on day 2 and take 6.5 days. As of now (the review point after day
4), it is 2 days ahead of schedule.
Job E should begin on day 1 and take 5 days. It was on time.
Day
Job
123456789 10 11
Job F was to begin on day 3, but maintenance forced a delay of 1.0 day. The job should now take 5
full days. It is now on schedule.
D
Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to
complete.
E
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have
been already plotted as blue lines).
Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on
top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks.
F
G
Now
LV
Transcribed Image Text:First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Job D was scheduled to begin early on day 2 and take 6.5 days. As of now (the review point after day 4), it is 2 days ahead of schedule. Job E should begin on day 1 and take 5 days. It was on time. Day Job 123456789 10 11 Job F was to begin on day 3, but maintenance forced a delay of 1.0 day. The job should now take 5 full days. It is now on schedule. D Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to complete. E Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks. F G Now LV
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Holt Mcdougal Larson Pre-algebra: Student Edition…
Holt Mcdougal Larson Pre-algebra: Student Edition…
Algebra
ISBN:
9780547587776
Author:
HOLT MCDOUGAL
Publisher:
HOLT MCDOUGAL
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill
College Algebra (MindTap Course List)
College Algebra (MindTap Course List)
Algebra
ISBN:
9781305652231
Author:
R. David Gustafson, Jeff Hughes
Publisher:
Cengage Learning