Today January 1, 2022, you have been named CFO of iSoftCloud, Inc., a startup in the cloud software industry. The previous CFO already committed to two projects down the road: Project A is about to start on January 1, 2028 (that is six years from today) and lasts for 6 years (it is closed down on December 31, 2033). On each January 1 of the calendar years of 2028 to 2033, Project A needs an infusion of capital (investment) of $1.0 million. The cost of capital (discount rate) for Project A is 10.0% Project B is about to start in a few minutes from your celebration of being named the CFO, in other words it has to start on January 1, 2022 (that is today) and lasts for 6 years (it is closed down on December 31, 2027). On each January 1 of the calendar years of 2022 (that is starting today) to 2027, Project B needs an infusion of capital (investment) of $1.0 million. The cost of capital (discount rate) for Project B is 15.0% What is the present value as of today, January 1, 2022, of the total funds you’ll need to invest for the two projects? If you have the option to postpone the starting date for Project B to start on the same date as Project A but that would require a capital infusion (investment) of $2.0 million on each January 1 of the calendar years of 2028 to 2033, would you do it? Assume the life, six years, and cost of capital (discount rate) of 15.0% for Project B are unchanged. Assume Project A starts on January 1, 2028 as described above and Project B starts today, on January 1, 2022, as described above, both last for six years and requires the yearly investments as described above. Your assistant reminds you that you still have to calculate the NPV for the two projects. She provides you with the following: The present value, as of today, of all the benefits from Project A is $3.0 million. The present value, as of today, of all the benefits from Project B is $4.0 million. What is the NPV? If you could cancel any of the two projects, would you? Which one and why?
Today January 1, 2022, you have been named CFO of iSoftCloud, Inc., a startup in the cloud software industry. The previous CFO already committed to two projects down the road: Project A is about to start on January 1, 2028 (that is six years from today) and lasts for 6 years (it is closed down on December 31, 2033). On each January 1 of the calendar years of 2028 to 2033, Project A needs an infusion of capital (investment) of $1.0 million. The cost of capital (discount rate) for Project A is 10.0% Project B is about to start in a few minutes from your celebration of being named the CFO, in other words it has to start on January 1, 2022 (that is today) and lasts for 6 years (it is closed down on December 31, 2027). On each January 1 of the calendar years of 2022 (that is starting today) to 2027, Project B needs an infusion of capital (investment) of $1.0 million. The cost of capital (discount rate) for Project B is 15.0% What is the present value as of today, January 1, 2022, of the total funds you’ll need to invest for the two projects? If you have the option to postpone the starting date for Project B to start on the same date as Project A but that would require a capital infusion (investment) of $2.0 million on each January 1 of the calendar years of 2028 to 2033, would you do it? Assume the life, six years, and cost of capital (discount rate) of 15.0% for Project B are unchanged. Assume Project A starts on January 1, 2028 as described above and Project B starts today, on January 1, 2022, as described above, both last for six years and requires the yearly investments as described above. Your assistant reminds you that you still have to calculate the NPV for the two projects. She provides you with the following: The present value, as of today, of all the benefits from Project A is $3.0 million. The present value, as of today, of all the benefits from Project B is $4.0 million. What is the NPV? If you could cancel any of the two projects, would you? Which one and why?
Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
Related questions
Question
Today January 1, 2022, you have been named CFO of iSoftCloud, Inc., a startup in the cloud software industry. The previous CFO already committed to two projects down the road:
- Project A is about to start on January 1, 2028 (that is six years from today) and lasts for 6 years (it is closed down on December 31, 2033). On each January 1 of the calendar years of 2028 to 2033, Project A needs an infusion of capital (investment) of $1.0 million. The cost of capital (discount rate) for Project A is 10.0%
- Project B is about to start in a few minutes from your celebration of being named the CFO, in other words it has to start on January 1, 2022 (that is today) and lasts for 6 years (it is closed down on December 31, 2027). On each January 1 of the calendar years of 2022 (that is starting today) to 2027, Project B needs an infusion of capital (investment) of $1.0 million. The cost of capital (discount rate) for Project B is 15.0%
- What is the
present value as of today, January 1, 2022, of the total funds you’ll need to invest for the two projects? - If you have the option to postpone the starting date for Project B to start on the same date as Project A but that would require a capital infusion (investment) of $2.0 million on each January 1 of the calendar years of 2028 to 2033, would you do it? Assume the life, six years, and cost of capital (discount rate) of 15.0% for Project B are unchanged.
- Assume Project A starts on January 1, 2028 as described above and Project B starts today, on January 1, 2022, as described above, both last for six years and requires the yearly investments as described above. Your assistant reminds you that you still have to calculate the NPV for the two projects. She provides you with the following:
- The present value, as of today, of all the benefits from Project A is $3.0 million.
- The present value, as of today, of all the benefits from Project B is $4.0 million.
What is the NPV? If you could cancel any of the two projects, would you? Which one and why?
Expert Solution
Step 1
Given:
Project A
Annual investment=$1 million
cost of capital=10%
benefit as of present value=$3 million
Project B
Annual investment=$1 million
cost of capital=15%
benefit as of present value=$4 million
Step by step
Solved in 5 steps
Recommended textbooks for you
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education