Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8, 6-9] On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,425,000. During 2024, costs of $2,170,000 were incurred, with estimated costs of $4,170,000 yet to be incurred. Billings of $2,704,000 were sent, and cash collected was $2,420,000. In 2025, costs incurred were $2,704,000 with remaining costs estimated to be $3,855,000. 2025 billings were $2,954,000, and $2,645,000 cash was collected. The project was completed in 2026 after additional costs of $3,970,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 2B Req 3A Req 3B

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected
on entire project [LO6-8, 6-9]
On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of
$8,425,000. During 2024, costs of $2,170,000 were incurred, with estimated costs of $4,170,000 yet to be incurred. Billings of
$2,704,000 were sent, and cash collected was $2,420,000.
In 2025, costs incurred were $2,704,000 with remaining costs estimated to be $3,855,000. 2025 billings were $2,954,000, and
$2,645,000 cash was collected. The project was completed in 2026 after additional costs of $3,970,000 were incurred. The
company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025.
Complete this question by entering your answers in the tabs below.
Req 1
Req 2A
Req 2B
Req 3A
Req 3B
Transcribed Image Text:Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8, 6-9] On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,425,000. During 2024, costs of $2,170,000 were incurred, with estimated costs of $4,170,000 yet to be incurred. Billings of $2,704,000 were sent, and cash collected was $2,420,000. In 2025, costs incurred were $2,704,000 with remaining costs estimated to be $3,855,000. 2025 billings were $2,954,000, and $2,645,000 cash was collected. The project was completed in 2026 after additional costs of $3,970,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 2B Req 3A Req 3B
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education