Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2024, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2025, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2025 billings were $2,790,000, and $2,515,000 cash was collected. The project was completed in 2026 after additional costs of $3,840,000 were incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 2B Req 3A Req 3B Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Note: Do not round intermediate calculations. Round your answers to the nearest dollar amount. Balance Sheet (Partial) At Dember 21 2025 Drov 11

Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 35E
icon
Related questions
Question

Plij answeraa

Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project
[LO6-9]
On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of
$8,120,000. During 2024, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of
$2,540,000 were sent, and cash collected was $2,290,000.
In 2025, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2025 billings were $2,790,000, and
$2,515,000 cash was collected. The project was completed in 2026 after additional costs of $3,840,000 were incurred. The
company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025.
Complete this question by entering your answers in the tabs below.
Req 1
Req 2A
Req 2B
Req 3A
Req 3B
Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025.
Note: Do not round intermediate calculations. Round your answers to the nearest dollar amount.
Balance Sheet (Partial)
At Dember 21
2025
Drov
11
Transcribed Image Text:Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2024, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2025, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2025 billings were $2,790,000, and $2,515,000 cash was collected. The project was completed in 2026 after additional costs of $3,840,000 were incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 2B Req 3A Req 3B Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Note: Do not round intermediate calculations. Round your answers to the nearest dollar amount. Balance Sheet (Partial) At Dember 21 2025 Drov 11
Expert Solution
steps

Step by step

Solved in 2 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L