Example: Given the following areas of cut and fill, complete the earthwork calculation using shrinkage factor of 20%, and draw the M.H.D. and the longitudinal profile of the earthworks and find the following: Net cut and fill volumes at each station. Limit of Economic Haul (L.E.H.). Free haul volume (F.H.V.). Overhaul volume (O.H.V.). Borrow and waste volumes Total cost of the earthworks If you know that: Cost of overhaul: 3000 ID/m³.station. Cost of free haul: 5000 ID/m³ Cost of borrow: 15000 ID/m³ Free haul distance (F.H.D): 300m Cost of waste =5000 ID/m³ Station 4 5 6. 9. 10 13 14 15 Area cut (m²) 12 16 10 6. Area Fill (m²) 10 13 16 8 12 18

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

please show the table and complete solution. thank you

Example: Given the following areas of cut and fill, complete the earthwork
calculation using shrinkage factor of 20%. and draw the M.H.D. and the longitudinal
profile of the earthworks and find the following:
Net cut and fill volumes at each station.
Limit of Economic Haul (L.E.H.).
Free haul volume (F.H.V.).
Overhaul volume (O.H.V.).
Borrow and waste volumes
Total cost of the earthworks
If you know that:
Cost of overhaul: 3000 ID/m³.station.
Cost of free haul: 5000 ID/m³
Cost of borrow: 15000 ID/m³
Free haul distance (F.H.D): 300m
Cost of waste =5000 ID/m³
Station
4
6.
10
13
14
15
Area cut (m²)
12
16
10
6.
Area Fill (m²)
10
13
16
12
18
Transcribed Image Text:Example: Given the following areas of cut and fill, complete the earthwork calculation using shrinkage factor of 20%. and draw the M.H.D. and the longitudinal profile of the earthworks and find the following: Net cut and fill volumes at each station. Limit of Economic Haul (L.E.H.). Free haul volume (F.H.V.). Overhaul volume (O.H.V.). Borrow and waste volumes Total cost of the earthworks If you know that: Cost of overhaul: 3000 ID/m³.station. Cost of free haul: 5000 ID/m³ Cost of borrow: 15000 ID/m³ Free haul distance (F.H.D): 300m Cost of waste =5000 ID/m³ Station 4 6. 10 13 14 15 Area cut (m²) 12 16 10 6. Area Fill (m²) 10 13 16 12 18
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Introduction to Material Study
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning