EXAMPLE 2.6 Determination of Aggregate Requirement for a Roadway Aggregates from a gravel pit are required for constructing a road embankment. The porosity of the aggregates at the gravel pit is 60%. The desired porosity of the compacted aggregates in the embank- ment is 25%. For a section of the embankment 7.5m wide x 0.6m compacted thickness x 1 km long, (a) calculate the volume of aggregates required. (b) Just before the construction of the embank- ment, a re-check of the porosity of the aggregates at the gravel pit was conducted. The porosity was 65% rather than 60% (an error of +8.3%), what extra percentage of aggregates would be required to construct the embankment. Assume a swell factor of 1.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
EXAMPLE 2.6 Determination of Aggregate Requirement for a Roadway
Aggregates from a gravel pit are required for constructing a road embankment. The porosity of the
aggregates at the gravel pit is 60%. The desired porosity of the compacted aggregates in the embank-
ment is 25%. For a section of the embankment 7.5m wide x 0.6m compacted thickness x 1 km
long, (a) calculate the volume of aggregates required. (b) Just before the construction of the embank-
ment, a re-check of the porosity of the aggregates at the gravel pit was conducted. The porosity was
65% rather than 60% (an error of +8.3%), what extra percentage of aggregates would be required
to construct the embankment. Assume a swell factor of 1.
Transcribed Image Text:EXAMPLE 2.6 Determination of Aggregate Requirement for a Roadway Aggregates from a gravel pit are required for constructing a road embankment. The porosity of the aggregates at the gravel pit is 60%. The desired porosity of the compacted aggregates in the embank- ment is 25%. For a section of the embankment 7.5m wide x 0.6m compacted thickness x 1 km long, (a) calculate the volume of aggregates required. (b) Just before the construction of the embank- ment, a re-check of the porosity of the aggregates at the gravel pit was conducted. The porosity was 65% rather than 60% (an error of +8.3%), what extra percentage of aggregates would be required to construct the embankment. Assume a swell factor of 1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Calculation of settlement
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning