Data Products, Inc., packages and distributes a variety of
personal computer-related products. A time study has
been conducted for a job packaging 3.5-inch personal
computer diskettes for shipment to customers. The job
requires a packager to place 20 diskettes in a rectangular
plastic bag, close the bag with a twist tie, and place the
filled bag into a bin, which is replaced by another worker
when it is filled. The job can be broken into four basic
elements. The elemental times (in minutes) were ob-
tained from the time study for 10 job cycles shown in the
following table.
a. Using an allowance factor of 16%, determine the stan-
dard time for this job.
b. Determine the number of cycles for this time study
such that the company would be 95% confident that the
average time from the time study is within 4% of the
true average cycle time.