Element 1 2 3 4 Performance Rating 80% 75 120 105 1 0.51 1.51 0.86 1.11 Click here for the Excel Data File Element 1 2 3 4 a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.) Element 1 2 3 2 3 0.56 0.46 1.51 1.46 0.86 0.76 1.16 1.11 Average cycle 4 5 6 0.46 0.46 0.46 1.46 1.46 1.51 0.81 0.86 0.81 1.16 1.16 1.21 b. Find the normal time for each element. (Round your answers to 3 decimal places.) Normal time

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
c. Assuming an allowance factor of 21 percent of job time, compute the standard time
for this job. (Round your answers to 3 decimal places.)
Element
1
2
3
4
Standard time
Transcribed Image Text:c. Assuming an allowance factor of 21 percent of job time, compute the standard time for this job. (Round your answers to 3 decimal places.) Element 1 2 3 4 Standard time
A time study was conducted on a job that contains four elements. The observed times
and performance ratings for six cycles are shown in the following table.
OBSERVATIONS (minutes per cycle)
Element
1
2
3
4
Performance
Rating
80%
75
120
105
1
0.51
1.51
0.86
1.11
Click here for the Excel Data File
Element
1
2
3
4
Element
1
2
3
4
2
0.56
1.51
0.86
1.16
a. Determine the average cycle time for each element. (Round your answers to 3
decimal places.)
Average cycle
3
0.46
1.46
0.76
1.11
Normal time
4
5
6
0.46 0.46 0.46
1.46 1.46
1.51
0.81
0.81
0.86
1.16 1.16 1.21
b. Find the normal time for each element. (Round your answers to 3 decimal places.)
Transcribed Image Text:A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. OBSERVATIONS (minutes per cycle) Element 1 2 3 4 Performance Rating 80% 75 120 105 1 0.51 1.51 0.86 1.11 Click here for the Excel Data File Element 1 2 3 4 Element 1 2 3 4 2 0.56 1.51 0.86 1.16 a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.) Average cycle 3 0.46 1.46 0.76 1.11 Normal time 4 5 6 0.46 0.46 0.46 1.46 1.46 1.51 0.81 0.81 0.86 1.16 1.16 1.21 b. Find the normal time for each element. (Round your answers to 3 decimal places.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.