Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 5,500 kits in week 2 Start assembling 11,000 kits in weeks 3, 4, and 5 Start assembling 9,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). - System unit: Lead Time = 1 week; Minimum order quantity = 19,000 Week 1 2 3 4 Gross requirements 5,500 11,000 11,000 Scheduled receipts Projected ending inventory: 12,500 Net requirements Planned receipts 5 11,000 6 9,000
Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 5,500 kits in week 2 Start assembling 11,000 kits in weeks 3, 4, and 5 Start assembling 9,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). - System unit: Lead Time = 1 week; Minimum order quantity = 19,000 Week 1 2 3 4 Gross requirements 5,500 11,000 11,000 Scheduled receipts Projected ending inventory: 12,500 Net requirements Planned receipts 5 11,000 6 9,000
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![Speakers: Lead Time = 1 week; Minimum order quantity = 9,500
Week
1
2
3
Gross requirements
Scheduled receipts
Projected ending inventory: 13,500
Net requirements
Planned receipts
Planned orders
500
4
CD-ROM drivers: Lead Time = 2 weeks; Minimum order quantity = 17,500
Week
1
2
3
4
Gross requirements
Scheduled receipts
Projected ending inventory: 16,500
Net requirements
Planned receipts
Planned orders
5
5
6
6](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fe7de3668-b478-431f-b784-348e1d0fecb3%2Fde54d050-47f0-4e7e-b6b3-a995b2552ee3%2Fk21flqw_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Speakers: Lead Time = 1 week; Minimum order quantity = 9,500
Week
1
2
3
Gross requirements
Scheduled receipts
Projected ending inventory: 13,500
Net requirements
Planned receipts
Planned orders
500
4
CD-ROM drivers: Lead Time = 2 weeks; Minimum order quantity = 17,500
Week
1
2
3
4
Gross requirements
Scheduled receipts
Projected ending inventory: 16,500
Net requirements
Planned receipts
Planned orders
5
5
6
6
![Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a
system unit, a keyboard, and an installation kit. These pieces are packed together and
shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the
level 0 kits. Complete the MRP records, using the following information:
• Production plans for complete kits are as follows:
Start assembling 5,500 kits in week 2
Start assembling 11,000 kits in weeks 3, 4, and 5
Start assembling 9,000 kits in week 6
• The gross requirements for the system unit have already been given to you. For the
remaining items, you will need to figure out the gross requirements.
• All scheduled receipts, lead times, and beginning inventory levels are shown.
Click the icon to view the MRP records.
Construct the material requirements plan for item System unit (enter your responses as
whole numbers).
System unit: Lead Time = 1 week; Minimum order quantity = 19,000
Week
1
2
3
4
Gross requirements
5,500
11,000 11,000
Scheduled receipts
Projected ending inventory: 12,500
Net requirements
Planned receipts
1964-47
425124
5
11,000
6
9,000](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fe7de3668-b478-431f-b784-348e1d0fecb3%2Fde54d050-47f0-4e7e-b6b3-a995b2552ee3%2Fyb3w9ht_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a
system unit, a keyboard, and an installation kit. These pieces are packed together and
shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the
level 0 kits. Complete the MRP records, using the following information:
• Production plans for complete kits are as follows:
Start assembling 5,500 kits in week 2
Start assembling 11,000 kits in weeks 3, 4, and 5
Start assembling 9,000 kits in week 6
• The gross requirements for the system unit have already been given to you. For the
remaining items, you will need to figure out the gross requirements.
• All scheduled receipts, lead times, and beginning inventory levels are shown.
Click the icon to view the MRP records.
Construct the material requirements plan for item System unit (enter your responses as
whole numbers).
System unit: Lead Time = 1 week; Minimum order quantity = 19,000
Week
1
2
3
4
Gross requirements
5,500
11,000 11,000
Scheduled receipts
Projected ending inventory: 12,500
Net requirements
Planned receipts
1964-47
425124
5
11,000
6
9,000
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.