dreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,600. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,390 $2,940 102 4,140 3,970 103 2,750 1,940 104 9,290 7,290 105 5,900 5,560 106 4,310 3,530 For general factory use 1,150 4,350 Factory overhead costs incurred on account, $6,470. Depreciation of machinery and equipment, $2,090. The factory overhead rate is $45 per machine hour. Machine hours used:

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Topic Video
Question
2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process
Bal.
Finished Goods
Bal.
3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.
Hildreth Company
Schedule of Unfinished Jobs
Direct
Factory
Job
Direct Labor
Materials
Overhead
Total
Balance of Work in Process, April 30
24
4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.
Hildreth Company
Schedule of Completed Jobs
Job
Direct
Factory
Direct Labor
Materials
Overhead
Total
Transcribed Image Text:2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month. Work in Process Bal. Finished Goods Bal. 3. Prepare a schedule of unfinished jobs to support the balance in the work in process account. Hildreth Company Schedule of Unfinished Jobs Direct Factory Job Direct Labor Materials Overhead Total Balance of Work in Process, April 30 24 4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account. Hildreth Company Schedule of Completed Jobs Job Direct Factory Direct Labor Materials Overhead Total
ntries and Schedules for Unfinished Jobs and Completed Jobs
ildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations:
. Materials purchased on account, $2,600.
. Materials requisitioned and factory labor used:
Job No.
Materials
Factory Labor
101
$3,390
$2,940
102
4,140
3,970
103
2,750
1,940
104
9,290
7,290
105
5,900
5,560
106
4,310
3,530
For general factory use
1,150
4,350
C. Factory overhead costs incurred on account, $6,470.
3. Depreciation of machinery and equipment, $2,090.
e. The factory overhead rate is $45 per machine hour. Machine hours used:
Job No.
Machine Hours
101
38
102
36
103
30
104
69
105
20
106
21
Total
214
f. Jobs completed: 101, 102, 103, and 105.
g. Jobs were shipped and customers were billed as follows: Job 101, $9,650; Job 102, $11,680; Job 105, $17,520.
Required:
1. Journalize the entries to record the summarized operations. If an amount box does not require an entry, leave it blank.
Transcribed Image Text:ntries and Schedules for Unfinished Jobs and Completed Jobs ildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: . Materials purchased on account, $2,600. . Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,390 $2,940 102 4,140 3,970 103 2,750 1,940 104 9,290 7,290 105 5,900 5,560 106 4,310 3,530 For general factory use 1,150 4,350 C. Factory overhead costs incurred on account, $6,470. 3. Depreciation of machinery and equipment, $2,090. e. The factory overhead rate is $45 per machine hour. Machine hours used: Job No. Machine Hours 101 38 102 36 103 30 104 69 105 20 106 21 Total 214 f. Jobs completed: 101, 102, 103, and 105. g. Jobs were shipped and customers were billed as follows: Job 101, $9,650; Job 102, $11,680; Job 105, $17,520. Required: 1. Journalize the entries to record the summarized operations. If an amount box does not require an entry, leave it blank.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education