Draw the PERT network associated with the following project: Activity Immediate Predecessor(s) A B C D E F G H A A B B C D E, F
Q: Examine the following spreadsheet: A C Clerk Hours Sales Flags 1 Jim 18 126 2 3 Kate 20 189 Judy 21…
A: The value will be equal to 105, because in the range of (A2:D5), consider it as a matrix, A2=(1,1)…
Q: 3. Using the same data in #2, a. Calculate Spearman's r. b. Which of the two correlation…
A: Two variables X Violent Incidents Y Officers Assigned A B C D E F G H I J X…
Q: help meee
A: To solve both problems, use the Critical Path Method (CPM) to determine the earliest and latest…
Q: shows a graph of 10 tasks. Determine the preceding dependency for each task.
A: As per the question we are given a task graph T having 10 vertices and we have to find the preceding…
Q: Given this set of daily service operations, and assuming a processing order of A-B-C-D-E: Number of…
A: Processing order of service operations = A-B-C-D-EService OperationNumber of Daily…
Q: The Adelaide University Judo Club offers 2 fitness programs to enhance player fitness performance…
A: Note: Since you have posted a question with multiple sub-parts, we will provide the solution only to…
Q: Examine the following spreadsheet: A B C D 1 Clerk Hours Sales Flags 2 Jim 18 126 2 3 Kate 14 158…
A: The data is given as,
Q: 12. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team.…
A:
Q: Time required in hours Finishing Product of Assembly Profu in Rs. 20 12 80 A 14 15 60 B C 15 14 30…
A:
Q: BAN 2010 consumption (C) for selected countries was as foiloWs Jordan 2.5 billion $, USA 100 billion…
A: The number of observations is the total number of values provided in the data set for a particular…
Q: New Zealand Travel... G Google S Add to MyRegistry Mail - sgorham@a. Part 4 of 6 (d) Find the…
A:
Q: We are interested in exploring the relationship between the weight of a vehicle and its fuel…
A: a. The scatter plot with the line of best fit can be obtained using EXCEL software. Enter the…
Q: 1. Teaching methods: A class of 30 computer science students were taught introductory computer…
A: The formula for the confidence interval for two proportions is,where,Since you have posted a…
Q: The network and communication systems attached to the smart grid, including the routers and…
A: Disclaimer: Since you have asked multiple questions, we will solve the first question for you. If…
Q: Part A B and C urgently need
A: Q
Q: Which of the following is a benefit of a within-groups design over a between-groups design?
A: Given,, A multiple choice question: To find, which of the following is a benefit of a within…
Q: A. The Managing Director of Shoprite Company is faced with the problem of assigning five senior…
A:
Q: The optimistic, most likely and pessimistic times of all activities of a project are given in che…
A:
Q: TN Communications provides cellular telephone services. The company is planning to expand into the…
A: We can express the distance between the tower and each city using the distance formula: distance =…
Q: hich worker should be assigned to which job? What is the total time required? (Hint: Use the…
A:
Q: Rauschenberg Manufacturing is investigating which locations would best position its new plant…
A:
Q: 4. A plant manager considers the operational cost per hour of five machine alternatives. The cost…
A: Given Information:
Q: How would the drawing look? Develop a network for the problem . Determine the total project…
A: In tackling the project, the initial step involves constructing a network diagram that visually…
Q: A B с O! 1 อ! 2 3 ! The figure above shows a supermarket checkout system with workers A, B, and C…
A: We have to find the order of the workers in a way that provides the highest total output.Given that…
Q: A human resource manager is investigating the relationship between job satisfaction and job…
A: Since we do only up to three sub parts of a problem, we'll doing the first three sub parts only.…
Q: 2. Jeremy, a police researcher, is concerned that police officers may not be assigned to areas where…
A: The question is about correlation Given : To find : a ) Null and alt. hypo b ) Value of Pearson's…
Q: For each task build the relevant network diagram 2. Add the task durations for each activity 3.…
A: The network diagram is The Foreward pass method…
Q: solve part d of the question provided.
A: Let X is the time to complete the critical path. X~Normalμ=20.17,σ2=5.14
Q: Construct index number of price from the following data by applying: 1)Fisher’s Ideal method…
A: Obtain the price index number of price from the following data by applying the Fisher’s Ideal…
Q: need help
A: a.n=8r=29the number of vertical lines is 8-1= 7 vertical linesThe number of crosses is equal to…
Q: The first three columns in the file $ wa\_wheat $ contain observations on wheat yield in the Western…
A: The objective of this question is to analyze the wheat yield data for the Chapman Valley Shire in…
Q: The City Commission of Nashville has decided to build a botanical garden and picnic area in the…
A:
Q: 2. State whether Rissa can complete this cycle within two months and comment on the efficiency of…
A: As per the instruction we will answer the subpart (2), (3), (4) As per the question, we have…
Q: 12. As player salaries have increased, the cost of attending baseball games has increased…
A: First we'll arrange the data in ascending order so it would be easy to count frequencies for every…
Q: Find the mean and median number of two-room houses in the four tracts. (Enter your answers to two…
A: Number of two room houses in the four tracts are : 28, 67, 98, 137
Q: Use the file on Blackboard called "Excel Databases.xlsx". Locate the Consumer Food tab. Test to…
A: 7. Let μ1 denote mean of metro region and μ2 denote the mean of Outside metro region. Hypothesis:…
Q: Using the priority list T6, T3, T7, T2, T5, T1, T9, T3, T4, schedule the project below with two…
A: Given the table Task Time required Predecessors T1 9 T2 12 T3 3 T4 7 T1 T5 10…
Q: 10 8. 10 W E 13 M G 10 15 12 10 19 (12 A G= Hilo, W = Worst Poke Place, L=Looks Good Poke, E = Eat…
A: Let us find the shortest routes and the respective time for delivery in the next steps.
Step by step
Solved in 3 steps with 1 images
- PT AIRCAP is undertaking a construction project with details on activities, predecessors, and time. Each activity is outlined in the following table. 1. Illustrate Network Planning using the principles of Activity on Arrow (AOA) and Activity on Node (AON).A meat processing factory performs tasks by a series of 4 operators. Below table lists for each of the four resource pools, the unit load and the number of resource units. Base on this information, compute the effective capacity of each of the resource pools. Which one is the bottleneck of the meat processing operation? operator 3 operator 1 operator 2 operator 4CHALLENGE ACTIVITY 9.10.2: Relational databases select and project. 457726.2979310.qx3zqy7 Jump to level 1 What operation should be performed if you wanted to know what airlines fly to Honolulu? Airline FlyRight 222 FlyRight 199 FlyRight 323 FlyRight 122 JetGreen 221 et Green 22 JetGreen 199 Flight Number Select[Ex: Gate="22" Check Next Gate 34 Detroit 13 Denver 34 Detroit 22 33 22 22 2 Destination Anchorage Anchorage Honolulu Denver Departure Time 08:49 08:56 09:24 09:30 09:51 09:53 09:55 Project[ Ex: Destination ] 3 4 1 ~ ~ D 2 3 4 Feedback?
- Seth is the personnel director at a consulting company. He is considering a leadership program for managers at a client company. There are a number of activities that must be completed before the program can be conducted, and he has the time needed for each activity (below). Develop a network for this problem. Determine the total project completion time and the critical path(s). Activity Immediate Predecessors Time (Days) A - 2 B - 5 C - 1 D B 10 E A, D 3 F C 6 G E, F 8Given the following Bayesian network structure G: A В C D E F G HQuestion 2 Jensen Tire & Auto is in the process of deciding whether to purchase a maintenance contract for its new computer wheel alignment and balancing machine. Managers feel that maintenance expense should be related to usage, and they collected the following information on weekly usage (hours) and annual maintenance expense (in hundreds of dollars). Weekly Usage (hours) Annual Maintenance Expense 13 17.0 10 22.0 20 30.0 28 37.0 32 47.0 17 30.5 24 32.5 31 39.0 40 51.5 40.0 38 a. Develop the estimated regression equation that relates annual maintenance expense to weekly usage. b. Test the significance of the relationship in part (a) at .05 level of significance. C. What is your conclusion at the .05 level of significance?
- Can someone help me with the following problems on excel. Thank youRecently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Activity Optimistic Most Likely A 4 B 3 C D E 4 1 3 8 7 5 4 8 Pessimistic 12 10 8 5 9 Start A B E Finish a. What is the expected completion time of the project? The expected completion time is 19 days. (Enter your response as an integer.) b. What is the probability of completing the project in 21 days? Refer to the standard normal table. The probability of completing the project in 21 days is N (Enter your response rounded to four decimal places.)Table 1.1 (below) is a record of the travelling times of the time taken for ten (10) employees to deliver packages, to ten (10) of their distribution centres in Trinidad. These centres are located in Chaguanas (I), Arima (II), Sangre Grande (III), Princes Town (IV), Manzanilla (V), Rio Claro (VI), San Juan (VII), Point Fortin(VIII), San Fernando (IX) and Port of Spain (X). Worker Worker 1 Worker 2 Worker 3 Worker 4 Worker 5 Worker 6 Worker 7 Worker 8 Worker 9 Worker 10 I 26 30 29 26 29 27 25 30 25 25 II 40 45 30 32 37 37 42 41 41 40 Table 1.1 - Employee Travelling time (minutes) III 27 30 20 25 27 30 30 26 29 23 IV 35 32 32 30 31 30 35 28 36 30 V 39 35 30 36 35 36 30 30 40 38 Area VI 70 75 83 80 85 90 69 87 90 88 VII 30 30 34 29 27 30 34 28 30 32 VIII 75 79 80 75 76 69 66 67 78 68 IX 63 62 62 60 60 57 58 58 60 62 X 30 32 30 29 30 35 36 37 34 28
- A Pre-Algebre: Pre-Algebrs Secti 9 Schoology 9 Winter Coordinate Graphing FP + wasdpa. schoology.com conor-assessment-delivery otart 54902000327action=onresume&submission d=7270805 Socrative ehallpass Students MYDE I DI. - Student Backpack -. C Clever | Portal Prince of Egypt Math POSSIBLE Ofra Haza performed the voice of Yocheved in eighteen of the twenty-one languages in which this movie was dubbed. What percent of the movies did she perform in? O 116% O 3.78% O 68% O 85.7% 3 4 56Consider the typical road network of Figure 1. It rep- resents an area of downtown Jacksonville, Florida. The streets are all one-way, with the arrows indicating the di- rection of traffic flow. The flow of traffic in and out of the network is measured in terms of vehicles per hour (vph). The figures given here are based on midweek peak traffic hours, 7 A.M. to 9 A.M. and 4 P.M. to 6 P.M. An increase of 2 percent in the overall flow should be al- lowed for during the Friday evening traffic flow. Let us construct a mathematical model that can be used to ana- lyze this network. 400 vph 800 vph 225 vph Hogan Street> 5 Duval Street Monroe Street 250 vph Figure 1 Downtown Jacksonville, Florida B Laura Street 350 vph 125 vph 300 vph 600 vphThe number of burglaries in a city is depicted in two different graphs below. Burglary Counts Graph A Burglaries 300 250 200- 150 100 50 0 Year 1 Year 2 Year 3 300 290 280 270 260 250 240 230 III II. Year 4 Year 2 Year 5 Burglary Counts Graph B 210 200 Year 1 Year 3 Year 4 Step 1 of 2: How many times more burglaries were there actually in Year 1 compared to Year 4? Round your answer to 2 decimal places. Year 5