Draw the Gantt Chart of M1, M2, M3. Due dates of the jobs are 16,14,10,8 in order. Use "FIFO" Processing Time (min) Routing Process and Machine Number OP-1 OP-3 M1 M3 M2 M3 M3 M1 M2 M1 OP-1 OP-2 OP-3 Job-1 4/M1 3/M2 2/M3 Job-2 1/M2 4/M14/M3 Job-3 3/M3 2/M2 3/M1 Job-4 3/M2 3/M3 1/M1 Job-1 Job-2 Job-3 Job-4 OP-2 M2 M1 M2 M3
Draw the Gantt Chart of M1, M2, M3. Due dates of the jobs are 16,14,10,8 in order. Use "FIFO" Processing Time (min) Routing Process and Machine Number OP-1 OP-3 M1 M3 M2 M3 M3 M1 M2 M1 OP-1 OP-2 OP-3 Job-1 4/M1 3/M2 2/M3 Job-2 1/M2 4/M14/M3 Job-3 3/M3 2/M2 3/M1 Job-4 3/M2 3/M3 1/M1 Job-1 Job-2 Job-3 Job-4 OP-2 M2 M1 M2 M3
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
Related questions
Question
![5. Draw the Gantt Chart of M1, M2, M3. Due dates of the jobs are 16,14,10,8 in order. Use "FIFO"
Processing Time (min)
Routing Process and Machine Number
OP-1
OP-3
OP-1 OP-2 OP-3
Job-1 4/M1 3/M2 2/M3
Job-2 1/M2 4/M1 4/M3
M1
M3
M2
M3
Job-3 3/M3 2/M2 3/M1
Job-4 3/M2 3/M3 1/M1
M3
M1
M2
M1
Job-1
Job-2
Job-3
Job-4
OP-2
M2
M1
M2
M3](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F081951e6-f346-4a60-ae13-602b45047e5f%2Feaa103c6-7f71-4f2a-a0f6-c112f332283c%2F8zjdmsb_processed.png&w=3840&q=75)
Transcribed Image Text:5. Draw the Gantt Chart of M1, M2, M3. Due dates of the jobs are 16,14,10,8 in order. Use "FIFO"
Processing Time (min)
Routing Process and Machine Number
OP-1
OP-3
OP-1 OP-2 OP-3
Job-1 4/M1 3/M2 2/M3
Job-2 1/M2 4/M1 4/M3
M1
M3
M2
M3
Job-3 3/M3 2/M2 3/M1
Job-4 3/M2 3/M3 1/M1
M3
M1
M2
M1
Job-1
Job-2
Job-3
Job-4
OP-2
M2
M1
M2
M3
![Job Shop Scheduling. Draw the Gantt Chart of M1, M2, M3. Due dates of the
jobs are 16, 14, 10, 8 in order. Use "FIFO"](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F081951e6-f346-4a60-ae13-602b45047e5f%2Feaa103c6-7f71-4f2a-a0f6-c112f332283c%2Fjdoaskd_processed.png&w=3840&q=75)
Transcribed Image Text:Job Shop Scheduling. Draw the Gantt Chart of M1, M2, M3. Due dates of the
jobs are 16, 14, 10, 8 in order. Use "FIFO"
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps with 8 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,