Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b). Draw a resource profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile. Only 10 labourers available at any time Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only Table 1(a) / Jadual 1(a) Activity / Aktiviti Activity Description / Penerangan aktiviti IPA* Duration (Days) / Tempoh (Hari) Labour / Buruh A Excavation & foundation / Pengorekan & asas - 6 4 B SOG A 3 3 C Framing / Pembingkaian B 10 4 D Plumbing / Perpaipan B 4 2 E Electrical wiring / Pendawaian elektrik C 3 3 F Drywall / Dinding kering C 5 3 G HVAC C 3 4 H Roof / Bumbung C 5 3 I Paint / Mengecat F 4 2 J HVAC Finish / Kemasan HVAC G, H 2 2 K Flooring / Lantai D, I 4 3 L Electrical finish / Kemasan elektrik E, H 1 2 M Punch list & cleanup / Senarai punch & pembersihan J, K, L 1 2 *Immediately Preceding Activities / Aktiviti Mendahului Serta-merta Table 1(b) / Jadual 1(b) ID Duration (days)/ Tempoh (hari) ES EF LS LF TF FF A 6 B 3 C 10 D 4 E 3 F 5 G 3 H 5 I 4 J 2 K 4 L 1 M 1
- Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b).
- Draw a resource profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile.
- Only 10 labourers available at any time
- Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only
Table 1(a) / Jadual 1(a)
Activity / Aktiviti |
Activity Description / Penerangan aktiviti |
IPA* |
Duration (Days) / Tempoh (Hari) |
Labour / Buruh |
A |
Excavation & foundation / Pengorekan & asas |
- |
6 |
4 |
B |
SOG |
A |
3 |
3 |
C |
Framing / Pembingkaian |
B |
10 |
4 |
D |
Plumbing / Perpaipan |
B |
4 |
2 |
E |
Electrical wiring / Pendawaian elektrik |
C |
3 |
3 |
F |
Drywall / Dinding kering |
C |
5 |
3 |
G |
HVAC |
C |
3 |
4 |
H |
Roof / Bumbung |
C |
5 |
3 |
I |
Paint / Mengecat |
F |
4 |
2 |
J |
HVAC Finish / Kemasan HVAC |
G, H |
2 |
2 |
K |
Flooring / Lantai |
D, I |
4 |
3 |
L |
Electrical finish / Kemasan elektrik |
E, H |
1 |
2 |
M |
Punch list & cleanup / Senarai punch & pembersihan |
J, K, L |
1 |
2 |
*Immediately Preceding Activities / Aktiviti Mendahului Serta-merta
Table 1(b) / Jadual 1(b)
ID |
Duration (days)/ Tempoh (hari) |
ES |
EF |
LS |
LF |
TF |
FF |
A |
6 |
|
|
|
|
|
|
B |
3 |
|
|
|
|
|
|
C |
10 |
|
|
|
|
|
|
D |
4 |
|
|
|
|
|
|
E |
3 |
|
|
|
|
|
|
F |
5 |
|
|
|
|
|
|
G |
3 |
|
|
|
|
|
|
H |
5 |
|
|
|
|
|
|
I |
4 |
|
|
|
|
|
|
J |
2 |
|
|
|
|
|
|
K |
4 |
|
|
|
|
|
|
L |
1 |
|
|
|
|
|
|
M |
1 |
|
|
|
|
|
|
Step by step
Solved in 10 steps with 13 images