Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 253,000 laptops per quarter but currently produces 75,900 units. The conversion cost per quarter is $9,108,000. There are 63,250 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 8 minutes of move time, 22 minutes of wait time, and 5 minutes of rework time. (All work is done by cell workers.) Required: 1. Compute the theoretical and actual velocities (per hour) and the theoretical and actual cycle times (minutes per unit produced). If required, round to one decimal place.   Theoretical Actual Velocity fill in the blank 1  laptops per hour fill in the blank 2  laptops per hour Cycle time fill in the blank 3  minutes per laptop fill in the blank 4  minutes per laptop 2. Compute the ideal and actual amounts of conversion cost assigned per laptop. If required, round your answers to the nearest cent. Assignment per unit (theoretically) $fill in the blank 5 Assignment per unit (actual) $fill in the blank 6 3. Calculate MCE. If required, round your answer to two decimal places. fill in the blank 7

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Cycle Time and Velocity, MCE

Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 253,000 laptops per quarter but currently produces 75,900 units. The conversion cost per quarter is $9,108,000. There are 63,250 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 8 minutes of move time, 22 minutes of wait time, and 5 minutes of rework time. (All work is done by cell workers.)

Required:

1. Compute the theoretical and actual velocities (per hour) and the theoretical and actual cycle times (minutes per unit produced). If required, round to one decimal place.

  Theoretical Actual
Velocity fill in the blank 1  laptops per hour fill in the blank 2  laptops per hour
Cycle time fill in the blank 3  minutes per laptop fill in the blank 4  minutes per laptop

2. Compute the ideal and actual amounts of conversion cost assigned per laptop. If required, round your answers to the nearest cent.

Assignment per unit (theoretically) $fill in the blank 5
Assignment per unit (actual) $fill in the blank 6

3. Calculate MCE. If required, round your answer to two decimal places.
fill in the blank 7

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.