Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 253,000 laptops per quarter but currently produces 75,900 units. The conversion cost per quarter is $9,108,000. There are 63,250 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 8 minutes of move time, 22 minutes of wait time, and 5 minutes of rework time. (All work is done by cell workers.) Required: 1. Compute the theoretical and actual velocities (per hour) and the theoretical and actual cycle times (minutes per unit produced). If required, round to one decimal place. Theoretical Actual Velocity fill in the blank 1 laptops per hour fill in the blank 2 laptops per hour Cycle time fill in the blank 3 minutes per laptop fill in the blank 4 minutes per laptop 2. Compute the ideal and actual amounts of conversion cost assigned per laptop. If required, round your answers to the nearest cent. Assignment per unit (theoretically) $fill in the blank 5 Assignment per unit (actual) $fill in the blank 6 3. Calculate MCE. If required, round your answer to two decimal places. fill in the blank 7
Cycle Time and Velocity, MCE
Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 253,000 laptops per quarter but currently produces 75,900 units. The conversion cost per quarter is $9,108,000. There are 63,250 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 8 minutes of move time, 22 minutes of wait time, and 5 minutes of rework time. (All work is done by cell workers.)
Required:
1. Compute the theoretical and actual velocities (per hour) and the theoretical and actual cycle times (minutes per unit produced). If required, round to one decimal place.
Theoretical | Actual | |||
Velocity | fill in the blank 1 | laptops per hour | fill in the blank 2 | laptops per hour |
Cycle time | fill in the blank 3 | minutes per laptop | fill in the blank 4 | minutes per laptop |
2. Compute the ideal and actual amounts of conversion cost assigned per laptop. If required, round your answers to the nearest cent.
Assignment per unit (theoretically) | $fill in the blank 5 |
Assignment per unit (actual) | $fill in the blank 6 |
3. Calculate MCE. If required, round your answer to two decimal places.
fill in the blank 7