Consider the information below and estimate the duration of the activities as well as the cost for each activity. Activity Name Quantity to be Installed Production Rate Number of Resources Duration Planned Cost Per Resource Other Cost (per unit) Total Cost Start Unit Unit/day with one resource No. (Each) Day $/day for each resource $/ Unit $ A 500 50 2 200 10 B 800 40 4 150 10 C 500 50 2 250 8 D 450 75 2 450 12 E 400 100 1 450 20 F 300 15 4 200 10 G 240 80 1 200 20 H 250 10 5 200 14 I 100 20 1 50 40 Project Cost -
Consider the information below and estimate the duration of the activities as well as the cost for each activity. Activity Name Quantity to be Installed Production Rate Number of Resources Duration Planned Cost Per Resource Other Cost (per unit) Total Cost Start Unit Unit/day with one resource No. (Each) Day $/day for each resource $/ Unit $ A 500 50 2 200 10 B 800 40 4 150 10 C 500 50 2 250 8 D 450 75 2 450 12 E 400 100 1 450 20 F 300 15 4 200 10 G 240 80 1 200 20 H 250 10 5 200 14 I 100 20 1 50 40 Project Cost -
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
- Consider the information below and estimate the duration of the activities as well as the cost for each activity.
Activity Name |
Quantity to be Installed |
Production Rate |
Number of Resources |
Duration |
Planned Cost Per Resource |
Other Cost (per unit) |
Total Cost |
Start |
Unit |
Unit/day with one resource |
No. (Each) |
Day |
$/day for each resource |
$/ Unit |
$ |
A |
500 |
50 |
2 |
|
200 |
10 |
|
B |
800 |
40 |
4 |
|
150 |
10 |
|
C |
500 |
50 |
2 |
|
250 |
8 |
|
D |
450 |
75 |
2 |
|
450 |
12 |
|
E |
400 |
100 |
1 |
|
450 |
20 |
|
F |
300 |
15 |
4 |
|
200 |
10 |
|
G |
240 |
80 |
1 |
|
200 |
20 |
|
H |
250 |
10 |
5 |
|
200 |
14 |
|
I |
100 |
20 |
1 |
|
50 |
40 |
|
Project Cost |
- |
|
|
|
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.