Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 8 7. C D 12 14 A 4 A, B 6. 12 4 6. 8. H C 4 6. 8. E.F.G 12 2.

A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
icon
Related questions
Question
Consider a project that has been modeled as follows:
Activity
Immediate Predecessors
Optimistic
Most Probable Pessimistic
A
8
3
7
7
6.
D
A
7
12
14
A
3
4
F
A, B
9.
12
C
6
8.
H.
C
4
6.
8.
E,F.G
7
12
H
12
13
14
K
D,IJ
3
4.
What is the probability it takes longer then 30 ?
O.12
O.83
O.17
O 22
B.
Transcribed Image Text:Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 8 3 7 7 6. D A 7 12 14 A 3 4 F A, B 9. 12 C 6 8. H. C 4 6. 8. E,F.G 7 12 H 12 13 14 K D,IJ 3 4. What is the probability it takes longer then 30 ? O.12 O.83 O.17 O 22 B.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
A First Course in Probability (10th Edition)
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
A First Course in Probability
A First Course in Probability
Probability
ISBN:
9780321794772
Author:
Sheldon Ross
Publisher:
PEARSON