Consider a project that costs $250 now and is expected to generate $98 in net revenues at the end of each of the next three years. If the MARR is 5%, the future worth of this project is __________. A. $18.24 B. $19.54 C. $22.33 D. $18.29
21. Consider a project that costs $250 now and is expected to generate $98 in net revenues at the end of each of the next three years. If the MARR is 5%, the future worth of this project is __________.
A. |
$18.24 |
|
B. |
$19.54 |
|
C. |
$22.33 |
|
D. |
$18.29 |
23. Machine X has an initial cost of $12,000 and annual maintenance of $700 per year. It has a useful life of four years and no salvage value at the end of that time. Machine Y costs $22,000 initially and has no maintenance costs during the first year. Maintenance is $200 at the end of the second year and increases by $200 per year thereafter. Machine Y has a useful life of eight years and an anticipated salvage value of $5,000 at the end of its useful life. If the MARR is 6%, what is the approximate Net Present Worth (NPW) of machine X?
A. |
-$28,563 |
|
B. |
-$25,852 |
|
C. |
-$32,085 |
|
D. |
-$22,318 |
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 2 images