Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource 1 has a processing time of 4 minutes per unit. Resource 2 has a processing time of 7 minutes per unit. Resource 3 has a processing time of 5 minutes per unit.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Consider a process consisting of three resources. Assume there exists unlimited demand for the product.

  • Resource 1 has a processing time of 4 minutes per unit.
  • Resource 2 has a processing time of 7 minutes per unit.
  • Resource 3 has a processing time of 5 minutes per unit.

 

 

PA 3-3 (Algo) Consider a process consisting of thre.
Consider a process consisting of three resources. Assume there exists unlimited demand for the product.
• Resource 1 has a processing time of 4 minutes per unit.
Resource 2 has a processing time of 7 minutes per unit.
• Resource 3 has a processing time of 5 minutes per unit.
Resource 1
Resource 2
Resource 3
The three resources are staffed by different workers individually. The flow diagram is shown above.
(Round your Part a answer to 3 decimal places. Enter all other answers as whole numbers.)
a. What is the capacity of resource 2?
0.143 units per minute
b. What is the bottleneck in the process?
Resource
2
c. What is the utilization of resource 2?
7 percent
How long does it take the process to produce 204 units starting with an
d.
3,264 minutes
empty system, assuming this is a worker-paced process?
Transcribed Image Text:PA 3-3 (Algo) Consider a process consisting of thre. Consider a process consisting of three resources. Assume there exists unlimited demand for the product. • Resource 1 has a processing time of 4 minutes per unit. Resource 2 has a processing time of 7 minutes per unit. • Resource 3 has a processing time of 5 minutes per unit. Resource 1 Resource 2 Resource 3 The three resources are staffed by different workers individually. The flow diagram is shown above. (Round your Part a answer to 3 decimal places. Enter all other answers as whole numbers.) a. What is the capacity of resource 2? 0.143 units per minute b. What is the bottleneck in the process? Resource 2 c. What is the utilization of resource 2? 7 percent How long does it take the process to produce 204 units starting with an d. 3,264 minutes empty system, assuming this is a worker-paced process?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Lean manufacturing
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.