Complete the chase production​ plan, using the following information. The only costs you need to consider here are​ layoff, hiring, and inventory costs. If you complete the plan​ correctly, your​ hiring, layoff, and inventory costs should match those given here. Month    Forecasted sales March    1,890 April    1,548 May    1,512 June    1,017 July    1,971 August    2,475 September    2,871 October    2,673 November    3,573 December    3,600 January    2,655 February    2,286

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Complete the chase production​ plan, using the following information. The only costs you need to consider here are​ layoff, hiring, and inventory costs. If you complete the plan​ correctly, your​ hiring, layoff, and inventory costs should match those given here.
Month    Forecasted sales
March    1,890
April    1,548
May    1,512
June    1,017
July    1,971
August    2,475
September    2,871
October    2,673
November    3,573
December    3,600
January    2,655
February    2,286
 
Fill in the production plan table below (enter your responses as whole numbers).
Sales in
worker
hours
to meet
sales
average = 260
Month
Forecasted
sales
Actual
workers
Actual
production
Layoffs
Hiring
Ending
inventory
Transcribed Image Text:Fill in the production plan table below (enter your responses as whole numbers). Sales in worker hours to meet sales average = 260 Month Forecasted sales Actual workers Actual production Layoffs Hiring Ending inventory
Totals
Costs
Cost of plan
Planning values
Starting inventory
Starting and ending workforce
Hours worked per month per worker
Hours per unit
Hiring cost per worker
Layoff cost per worker
Monthly per-unit holding cost
Layoff
309
$927,000
Hiring
Inventory
309
24,000
$1,236,000 $216,000
$2,379,000
2,000
234
360
40
$4,000
$3,000
$9
Transcribed Image Text:Totals Costs Cost of plan Planning values Starting inventory Starting and ending workforce Hours worked per month per worker Hours per unit Hiring cost per worker Layoff cost per worker Monthly per-unit holding cost Layoff 309 $927,000 Hiring Inventory 309 24,000 $1,236,000 $216,000 $2,379,000 2,000 234 360 40 $4,000 $3,000 $9
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.