CN started a three-year contract to build a new university campus on 1 April 20X4. The contract had a fixed price of $90 million. CN will satisfy the performance obligation over time. CN incurred costs to 31 March 20X5 of $77 million and estimated that a further $33 million would need to be spent to complete the contract. CN measures the progress of contracts using work completed compared to contract price. At 31 March 20X5, a surveyor valued the work completed to date at $63 million. Select the correct amounts to be shown in revenue and cost of sales in the statement of profit or loss for the year ended 31 March 20X5? Revenue Cost of sales $63 million $77 million $57 million $83 million
CN started a three-year contract to build a new university campus on 1 April 20X4. The contract had a fixed price of $90 million. CN will satisfy the performance obligation over time. CN incurred costs to 31 March 20X5 of $77 million and estimated that a further $33 million would need to be spent to complete the contract.
CN measures the progress of contracts using work completed compared to contract price.
At 31 March 20X5, a surveyor valued the work completed to date at $63 million.
Select the correct amounts to be shown in revenue and cost of sales in the statement of profit or loss for the year ended 31 March 20X5?
Revenue Cost of sales
$63 million $77 million
$57 million $83 million