3. For the following seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project duration. Then go through a repetitive process to expedite the project on a least-cost basis until the project is crashed. The solution should include the precedence diagram and calculations for each activity, and then the cyclical calculation to shorten the project activity by activity in a least-cost manner. What is the total cost of the crashed project? Why is this less than the sum of the crashed costs for the seven activities? Please use Table A (Table A-2.pdf Please provide a detailed answer to this question. Table A Activity Relationships Normal Duration Crash Duration Normal Cost Crash Cost A B C D F F G A: FS B: FS C: FS D: FS A: FS C, E, F: FS 3 4 3 4 4 5 6 2 3 1 2 2 2 4 $3,000 $4,000 $6,500 $6,000 $3,500 $2,200 $3,900 $3.150 $4,250 $7,000 $6,500 $3,900 $2,725 $5,00

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
3. For the following seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES,
EF, LS, LF, TF), and the project duration. Then go through a repetitive process to expedite the project on a least-cost basis until the
project is crashed. The solution should include the precedence diagram and calculations for each activity, and then the cyclical
calculation to shorten the project activity by activity in a least-cost manner. What is the total cost of the crashed project? Why is this
less than the sum of the crashed costs for the seven activities? Please use Table A (Table A-2.pdf Please provide a detailed
answer to this question.
Transcribed Image Text:3. For the following seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project duration. Then go through a repetitive process to expedite the project on a least-cost basis until the project is crashed. The solution should include the precedence diagram and calculations for each activity, and then the cyclical calculation to shorten the project activity by activity in a least-cost manner. What is the total cost of the crashed project? Why is this less than the sum of the crashed costs for the seven activities? Please use Table A (Table A-2.pdf Please provide a detailed answer to this question.
Table A
Activity Relationships Normal Duration Crash Duration Normal Cost Crash Cost
A
B
C
D
F
F
G
A: FS
B: FS
C: FS
D: FS
A: FS
C, E, F: FS
3
4
3
4
4
5
6
2
3
1
2
2
2
4
$3,000
$4,000
$6,500
$6,000
$3,500
$2,200
$3,900
$3.150
$4,250
$7,000
$6,500
$3,900
$2,725
$5,00
Transcribed Image Text:Table A Activity Relationships Normal Duration Crash Duration Normal Cost Crash Cost A B C D F F G A: FS B: FS C: FS D: FS A: FS C, E, F: FS 3 4 3 4 4 5 6 2 3 1 2 2 2 4 $3,000 $4,000 $6,500 $6,000 $3,500 $2,200 $3,900 $3.150 $4,250 $7,000 $6,500 $3,900 $2,725 $5,00
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Knowledge Booster
Cost control
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning