Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $6.00) $18.00 Direct labor (0.5 hr. @ $9.00) 4.50 Total prime cost $22.50 During the first month of the year, the Boise plant produced 30,000 belts. Actual leather purchased was 110,000 strips at $3.90 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 30,000 hours at $13.50 per hour. Required: 1. Compute the costs of leather and direct labor that should be incurred for the production of 30,000 leather belts. Materials $ Labor $ 2. Compute the total budget variances for materials and labor. Total Budget Variance Materials $ Labor $ 3. Conceptual Connection: Would you consider these variances material with a need for investigation?
Budget Variances, Materials and Labor
Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a
Leather (3 strips @ $6.00) | $18.00 |
Direct labor (0.5 hr. @ $9.00) | 4.50 |
Total prime cost | $22.50 |
During the first month of the year, the Boise plant produced 30,000 belts. Actual leather purchased was 110,000 strips at $3.90 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 30,000 hours at $13.50 per hour.
Required:
1. Compute the costs of leather and direct labor that should be incurred for the production of 30,000 leather belts.
Materials | $ |
Labor | $ |
2. Compute the total budget variances for materials and labor.
Total |
||
Materials | $ | |
Labor | $ |
3. Conceptual Connection: Would you consider these variances material with a need for investigation?
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)