← Chapter 17 - Homework Question 4 of 5 View Policies Show Attempt History < > Current Attempt in Progress 9.64/20 On March 1, 2025, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2027. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2025, 2026, and 2027 are given below. 2025 2026 2027 Contract costs incurred during the year $2,880,000 $2,230,000 $2,190,000 Estimated costs to complete the contract at 12/31 3,520,000 2,190,000 -0- Billings to Fabrik during the year 3,200,000 3,500,000 1,700,000 (a1) Your answer is correct. Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2025. (Ignore income taxes.) (If answer is 0, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Costs to Date (12/31/25) Estimated Costs to Complete Estimated Total Costs Percent Complete Costs Incurred Revenue Recognized Profit/(Loss) Recognized in 2025 eTextbook and Media Solution (a2) 2025 - Your answer is partially correct. +A A 2,880,000 3,520,000 6,400,000 -2,880,000 45 % 3,780,000 +A $ 900,000 = SUPPORT Assistance Used Attempts: unlimited Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2026. (Ignore income taxes.) (If answer is O, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Estimated Costs to Complete Costs to Date (12/31/26) Estimated Total Costs Percent Complete Costs Incurred in 2026 Revenue Recognized in 2026 Profit/(Loss) Recognized in 2026 eTextbook and Media Solution Save for Later (a3) 2026 +A +A $ +A -4,460,000 5,110,000 7,300,000 -2,230,000 70 % 2,100,000 -130,000 Assistance Used Attempts: unlimited Submit Answer The parts of this question must be completed in order. This part will be available when you complete the part above. (b) The parts of this question must be completed in order. This part will be available when you complete the part above.
← Chapter 17 - Homework Question 4 of 5 View Policies Show Attempt History < > Current Attempt in Progress 9.64/20 On March 1, 2025, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2027. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2025, 2026, and 2027 are given below. 2025 2026 2027 Contract costs incurred during the year $2,880,000 $2,230,000 $2,190,000 Estimated costs to complete the contract at 12/31 3,520,000 2,190,000 -0- Billings to Fabrik during the year 3,200,000 3,500,000 1,700,000 (a1) Your answer is correct. Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2025. (Ignore income taxes.) (If answer is 0, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Costs to Date (12/31/25) Estimated Costs to Complete Estimated Total Costs Percent Complete Costs Incurred Revenue Recognized Profit/(Loss) Recognized in 2025 eTextbook and Media Solution (a2) 2025 - Your answer is partially correct. +A A 2,880,000 3,520,000 6,400,000 -2,880,000 45 % 3,780,000 +A $ 900,000 = SUPPORT Assistance Used Attempts: unlimited Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2026. (Ignore income taxes.) (If answer is O, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Estimated Costs to Complete Costs to Date (12/31/26) Estimated Total Costs Percent Complete Costs Incurred in 2026 Revenue Recognized in 2026 Profit/(Loss) Recognized in 2026 eTextbook and Media Solution Save for Later (a3) 2026 +A +A $ +A -4,460,000 5,110,000 7,300,000 -2,230,000 70 % 2,100,000 -130,000 Assistance Used Attempts: unlimited Submit Answer The parts of this question must be completed in order. This part will be available when you complete the part above. (b) The parts of this question must be completed in order. This part will be available when you complete the part above.
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
on march 1 2025 pechstein company contracted to construct a factory building for Fabrik Manufacturing Inc., for a total contract price of $8,400,000.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education