Cash Payback Period, Net Present Value Analysis, and Qualitative Considerations The plant manager of Shenzhen Electronics Company is considering the purchase of new automated assembly equipment. The new equipment will cost $102,000. manager believes that the new investment will result in direct labor savings of $34,000 per year for 10 years. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 1.833 1.736 1.690 1.626 1.528 2.673 2.487 2.402 2.283 2.106 3.465 3.170 3.037 2.855 2.589 4.212 3.791 3.605 3.353 2.991 6. 4.917 4.355 4.111 3.785 3.326 7. 5.582 4.868 4.564 4.160 3.605 8 6.210 5.335 4.968 4.487 3.837 9. 6.802 5.759 5.328 4.772 4.031 10 7.360 6.145 5.650 5.019 4.192 a. What is the payback period on this project? years b. What is the net present value, assuming a 12% rate of return? Use the table provided above. Round to the nearest whole dollar. Net present value c. What else should the manager consider in the analysis? Previous Check My Work 3 more Check My Work uses remaining. Save and Exit Submit Assignment f Email Instructor

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
еBook
Print Item
Cash Payback Period, Net Present Value Analysis, and Qualitative Considerations
The plant manager of Shenzhen Electronics Company is considering the purchase of new automated assembly equipment. The new equipment will cost $102,000. The
manager believes that the new investment will result in direct labor savings of $34,000 per year for 10 years.
Present Value of an Annuity of $1 at Compound Interest
Year
6%
10%
12%
15%
20%
1
0.943
0.909
0.893
0.870
0.833
1.833
1.736
1.690
1.626
1.528
3
2.673
2.487
2.402
2.283
2.106
3.465
3.170
3.037
2.855
2.589
4.212
3.791
3.605
3.353
2.991
6.
4.917
4.355
4.111
3.785
3.326
5.582
4.868
4.564
4.160
3.605
8
6.210
5.335
4.968
4.487
3.837
9.
6.802
5.759
5.328
4.772
4.031
10
7.360
6.145
5.650
5.019
4.192
a. What is the payback period on this project?
years
b. What is the net present value, assuming a 12% rate of return? Use the table provided above. Round to the nearest whole dollar.
Net present value
c. What else should the manager consider in the analysis?
Previous
Next
Check My Work 3 more Check My Work uses remaining.
Save and Exit
|Submit Assignment for G
Emal Instructor
Transcribed Image Text:еBook Print Item Cash Payback Period, Net Present Value Analysis, and Qualitative Considerations The plant manager of Shenzhen Electronics Company is considering the purchase of new automated assembly equipment. The new equipment will cost $102,000. The manager believes that the new investment will result in direct labor savings of $34,000 per year for 10 years. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 3.465 3.170 3.037 2.855 2.589 4.212 3.791 3.605 3.353 2.991 6. 4.917 4.355 4.111 3.785 3.326 5.582 4.868 4.564 4.160 3.605 8 6.210 5.335 4.968 4.487 3.837 9. 6.802 5.759 5.328 4.772 4.031 10 7.360 6.145 5.650 5.019 4.192 a. What is the payback period on this project? years b. What is the net present value, assuming a 12% rate of return? Use the table provided above. Round to the nearest whole dollar. Net present value c. What else should the manager consider in the analysis? Previous Next Check My Work 3 more Check My Work uses remaining. Save and Exit |Submit Assignment for G Emal Instructor
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education