Case study The contractor received a submittal package from the curtain wall subcontractor. Per the specifications, product data, shop drawings, finish samples, fabrication sample, product test reports, field test reports, and design analysis are required. The product data, shop drawings, and finish samples are specified as action submittals, the other submittals are specified to be informational submittals. The curtain wall shown on the drawings was a generic system and the specifications provided a list of three acceptable systems, which had slightly different methods of fabrication and attachment to the building structure. When the curtain wall installation is 10% complete, the specifications call for the contractor to perform water spray and air leakage tests. The results of these tests are to be submitted to the architect. The curtain wall manufacturer prepared the action submittals, the product test reports, and the design analysis and gave them to the subcontractor to submit. The contractor had the testing agency prepare the field test reports. Near the completion of the project, the contractor is required to submit maintenance information for the curtain walls for the operation and maintenance manuals. Answer the questions on the next page based on the Case Study. Question A: What should the subcontractor do with the submittals prepared by the manufacturer? A. Send them to the architect/engineer for review B. Send them to the owner for review C. Send them to the contractor for review D. Send separate copies for concurrent review by the architect/engineer and the contractor Question B: What should the architect/engineer do after reviewing the product data, finish samples, and shop drawings? A. Take no responsive action and return all copies to the contractor B. Take responsive action, retain the number of copies the architect/engineered required, and return the remainder to the subcontractor C. Take no responsive action and retain all copies in the project files D. Take responsive action, retain the number of copies the architect/engineered required, and return the remainder to the contractor Question C: True or False? The maintenance information submitted would be considered a maintenance material submittal. A. True B. False

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Case study
The contractor received a submittal package from the curtain wall subcontractor. Per the specifications, product
data, shop drawings, finish samples, fabrication sample, product test reports, field test reports, and design
analysis are required.
The product data, shop drawings, and finish samples are specified as action submittals, the other submittals are
specified to be informational submittals. The curtain wall shown on the drawings was a generic system and the
specifications provided a list of three acceptable systems, which had slightly different methods of fabrication and
attachment to the building structure.
When the curtain wall installation is 10% complete, the specifications call for the contractor to perform water
spray and air leakage tests. The results of these tests are to be submitted to the architect. The curtain wall
manufacturer prepared the action submittals, the product test reports, and the design analysis and gave them to
the subcontractor to submit. The contractor had the testing agency prepare the field test reports.
Near the completion of the project, the contractor is required to submit maintenance information for the curtain
walls for the operation and maintenance manuals.
Answer the questions on the next page based on the Case Study.
Question A: What should the subcontractor do with the submittals prepared by the manufacturer?
A. Send them to the architect/engineer for review
B. Send them to the owner for review
C. Send them to the contractor for review
D. Send separate copies for concurrent review by the architect/engineer and the contractor
Question B: What should the architect/engineer do after reviewing the product data, finish samples, and shop
drawings?
A. Take no responsive action and return all copies to the contractor
B. Take responsive action, retain the number of copies the architect/engineered required, and return the
remainder to the subcontractor
C. Take no responsive action and retain all copies in the project files
D. Take responsive action, retain the number of copies the architect/engineered required, and return the
remainder to the contractor
Question C: True or False? The maintenance information submitted would be considered a maintenance
material submittal.
A. True
B. False
Transcribed Image Text:Case study The contractor received a submittal package from the curtain wall subcontractor. Per the specifications, product data, shop drawings, finish samples, fabrication sample, product test reports, field test reports, and design analysis are required. The product data, shop drawings, and finish samples are specified as action submittals, the other submittals are specified to be informational submittals. The curtain wall shown on the drawings was a generic system and the specifications provided a list of three acceptable systems, which had slightly different methods of fabrication and attachment to the building structure. When the curtain wall installation is 10% complete, the specifications call for the contractor to perform water spray and air leakage tests. The results of these tests are to be submitted to the architect. The curtain wall manufacturer prepared the action submittals, the product test reports, and the design analysis and gave them to the subcontractor to submit. The contractor had the testing agency prepare the field test reports. Near the completion of the project, the contractor is required to submit maintenance information for the curtain walls for the operation and maintenance manuals. Answer the questions on the next page based on the Case Study. Question A: What should the subcontractor do with the submittals prepared by the manufacturer? A. Send them to the architect/engineer for review B. Send them to the owner for review C. Send them to the contractor for review D. Send separate copies for concurrent review by the architect/engineer and the contractor Question B: What should the architect/engineer do after reviewing the product data, finish samples, and shop drawings? A. Take no responsive action and return all copies to the contractor B. Take responsive action, retain the number of copies the architect/engineered required, and return the remainder to the subcontractor C. Take no responsive action and retain all copies in the project files D. Take responsive action, retain the number of copies the architect/engineered required, and return the remainder to the contractor Question C: True or False? The maintenance information submitted would be considered a maintenance material submittal. A. True B. False
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Engineering symbols
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning