Calculate number of transit mixers (TM) required for transporting concrete from central batching plant to site. The cycle time data of a 6 m² typical transit mixers is given below: O Loading time of TM = 6.0 minutes. O Travel time of loaded TM to site= 30 minutes. Average waiting time at site = 5.0 minutes Discharge time of concrete at site through concrete pump = 15 minutes. O Travel time for return trip =24 minutes. If the central batching plant having average output of 60 m³/hr is to run continuously, work out the requirement of no. of concrete pumps TM.
Calculate number of transit mixers (TM) required for transporting concrete from central batching plant to site. The cycle time data of a 6 m² typical transit mixers is given below: O Loading time of TM = 6.0 minutes. O Travel time of loaded TM to site= 30 minutes. Average waiting time at site = 5.0 minutes Discharge time of concrete at site through concrete pump = 15 minutes. O Travel time for return trip =24 minutes. If the central batching plant having average output of 60 m³/hr is to run continuously, work out the requirement of no. of concrete pumps TM.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![Calculate number
of transit mixers
(TM) required for
transporting concrete
from central batching
plant to site. The cycle
time data of a 6 m³
typical transit mixers is
given below:
O Loading time of TM =
6.0 minutes.
O Travel time of loaded TM
to site= 30 minutes.
Average waiting time at
site = 5.0 minutes
Discharge time of
concrete at site through
concrete pump = 15
minutes.
Travel time for return trip
= 24 minutes.
If the central batching
plant having average
output of 60 m³/hr is to
run continuously, work
out the requirement of
no. of concrete pumps
and TM.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fbb4f7f44-9258-4dfc-a2d9-782a54ef407e%2Fedc39438-2842-485a-b14d-112b1af46d3b%2Fhbn45nu_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Calculate number
of transit mixers
(TM) required for
transporting concrete
from central batching
plant to site. The cycle
time data of a 6 m³
typical transit mixers is
given below:
O Loading time of TM =
6.0 minutes.
O Travel time of loaded TM
to site= 30 minutes.
Average waiting time at
site = 5.0 minutes
Discharge time of
concrete at site through
concrete pump = 15
minutes.
Travel time for return trip
= 24 minutes.
If the central batching
plant having average
output of 60 m³/hr is to
run continuously, work
out the requirement of
no. of concrete pumps
and TM.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning