Brainy Company started the construction of a building for a customer at a fixed contract price of P2,000,000 on January 1, 2019. On the same date, the customer paid a mobilization fee equal to 5% of contract price that will be deductible from the first billing. The outcome of construction contract can be estimated reliably except in 2019 which is the start of the project. The company billed the customer equivalent to 30%, 20% and 40% of the contract price during 2019, 2020 and 2021, respectively. The remaining billing was made at the year of completion of the project. The company made collection from the customer at the end of 2019, 2020 and 2021, in the amount of P240,000, P900,000 and P360,000, respectively. Direct costs related to the said project (see image below). 1. What is the Percentage of completion in 2020? 2. How much is the Construction Revenue to be recognized in 2020? 3. How much is the Gross Income (Loss) to be recognized in 2021? 4. How much is the balance of Account Receivable at December 31, 2021? 5. How much is the Contract Asset/Liability at December 31, 2021?

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter12: Balanced Scorecard And Other Performance Measures
Section: Chapter Questions
Problem 11MC: Dixon Construction Materials has collected this information: Based on this Information, what is the...
icon
Related questions
Question

Brainy Company started the construction of a building for a customer at a fixed contract price of P2,000,000 on January 1, 2019. On the same date, the customer paid a mobilization fee equal to 5% of contract price that will be deductible from the first billing. The outcome of construction contract can be estimated reliably except in 2019 which is the start of the project. The company billed the customer equivalent to 30%, 20% and 40% of the contract price during 2019, 2020 and 2021, respectively. The remaining billing was made at the year of completion of the project. The company made collection from the customer at the end of 2019, 2020 and 2021, in the amount of P240,000, P900,000 and P360,000, respectively. Direct costs related to the said project (see image below).
1. What is the Percentage of completion in 2020?

2. How much is the Construction Revenue to be recognized in 2020?

3. How much is the Gross Income (Loss) to be recognized in 2021?

4. How much is the balance of Account Receivable at December 31, 2021?

5. How much is the Contract Asset/Liability at December 31, 2021?

Cost incurred to date
Estimated costs to complete
2019
720,000
1,680,000
2020
1,600,000
500,000
2021
1,740,000
100,000
Transcribed Image Text:Cost incurred to date Estimated costs to complete 2019 720,000 1,680,000 2020 1,600,000 500,000 2021 1,740,000 100,000
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

How about these questions:

1. How much is the balance of Account Receivable at December 31, 2021?

2. How much is the Contract Asset/Liability at December 31, 2021?

Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College