Bhojraj Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 3 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 9 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 3 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Line Item Description Traditional Philosophy Lean Manufacturing Philosophy Value-added time Non-value-added time Total lead time 779 33 Value-added ratio (as a percent)
Bhojraj Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 3 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 9 minutes.
Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 3 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.
Line Item Description | Traditional Philosophy | Lean Manufacturing Philosophy |
---|---|---|
Value-added time | ||
Non-value-added time | ||
Total lead time | 779 | 33 |
Value-added ratio (as a percent) |
Step by step
Solved in 2 steps