Bee, Andrew& Al Shanawa (MGA, Inc.), a Certified Public Accountant in Marietta, has approached your construction management firm requesting a feasibility study that includes a plan for construction activities that need to be completed by the start of the Spring semester. After meeting with your shareholders to determine whether or not it is in the company's best interest to go after this work for these particular people, you decide that it is worth the risk. During a preconstruction meeting, the project team develops activities and duration estimates that will drive the schedule, and provide enough information to the owner of your company to make a decision. The transcript from the meeting is on Page 3. These steps are the deliverables required for the midterm. After reading the transcript, complete the steps, in order, and answer the questions below. Step 1- Develop a dependency table showing activity relationships Step 2- Layout an AON network diagram, and develop a legend or key for each activity box. Step 3-Perform a Forward Pass, Backward Pass, and Float Calculation and clearly indicate the critical path with color or highlighting. Remember, a clear presentation to the owner (that's me) is crucial! This should be done by hand only. Use the fully constructed AON network diagram (steps 1-3 above) indicating the critical path, (a calendar with dates is useful to reference, but not a required deliverable) to answer the following questions: a. What activities make up the critical path? b. When is the proposed finish date? c. What are two near-critical activities? 2 d. If the Architect changes their mind, and the exterior siding material is delayed and does not arrive until Wednesday, November 6, 2024, causing this to be the earliest starting date for the activity, does this impact the finish date listed in question b.? How do you know? e. What is the new revised finish date if the carpenters that are responsible for the exterior siding cannot work the week of the 4th of November, assuming the material is delayed, and could only start back on Tuesday, November 12th? How do you know? f. If the insulation material is delayed and does not arrive until Tuesday, November 12th, 2024, causing this to be the earliest starting date for the activity, does this impact the finish date listed in question b.? (ignore previous delays in questions d. and e.) How do you know? g. What is the new revised finish date if the insulators cannot work the week of the 11th of November, assuming material is delayed, and could only start back on Monday, November 18th? How do you know? h. If the Rough Electric takes 4 additional workdays, does this impact the overall project? If so, by how many days? (ignore d. through g.) . If Dr. Moore and Dr. Al- Shenawa want to visit the jobsite on Thursday, November 21st, and the day after to play golf with Bubba, and it shuts down all work for both days because Bubba is a big hitter and everybody wants to watch, which activities will be impacted? (ignore d. through h.) Transcript "Alright. We need to start immediately, no time for delay. Use Monday September 30, 2024, as a starting point" "Bossman, do we need to work weekends and holidays to knock this thing out? I have some things planned for the weekends coming up and Thanksgiving." "No, we don't need to extend resources for that. No weekends or holidays, standard 5 day work week should do it. Well, we will certainly have to start with SITEWORK, and this will take 4 days probably" "After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in 12 days" "Since we are talking about the outside work, we would have to include 4 days for LANDSCAPING before we CLOSEOUT THE PROJECT" "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete" "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!" "How much time will we need for EXTERIOR PAINTING?" "5 days" "Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then" "Yep, but let's get back to the beginning. The ROUGH PLUMBING should take 12 days, and needs to start 5 days after FORM/POUR SLAB starts, which will take at least 7 days to complete" "Do we have to wait until the UNDERGROUND UTILITIES are complete before we FORM/POUR SLAB?" "No, FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is complete before starting to FRAME WALLS" "FRAME WALLS is crucial, let's put 5 days for that. Its completion allow ROUGH ELECTRIC, FRAME ROOF, and the WINDOWS/DOORS to start" "Okay, so let's say 7 days for ROUGH ELECTRIC, 10 days to hang WINDOWS/DOORS and the carpenters can FRAME ROOF in 7 days" "If the boys can frame the roof in 7 days, surely the roofers can FINISH ROOF right after that in 3 days as well" "Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of 5 days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done either" "EXTERIOR SIDING can start after the WINDOWS/DOORS, and should take 5 days to complete" "Slow down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF firstbefore DRYWALL starts this time!" "10-4 Boss" "INSULATION might take 3 days, but needs to wait on ROUGH ELECTRIC, ROUGH MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be complete before DRYWALL is complete " "We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND UTILITIES" "Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING, and FINISH MECHANICAL, and know that all three need DRYWALL to be complete before starting" "Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete, and needs to happen after DRYWALL and before FINISH ELECTRIC" "That should do it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3 FINISH MEP activities and LANDSCAPING to tie up any loose ends" "Sounds good. Great work boys!"|

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

Step 1 – Develop a dependency table showing activity relationships
Step 2 – Layout an AON network diagram, and develop a legend or key for
each activity box.
Step 3 – Perform a Forward Pass, Backward Pass, and Float Calculation and
clearly indicate the critical path with color or highlighting.  please help me with this with the information provided and answer the questions

please help I am struggling with this

Bee, Andrew& Al Shanawa (MGA, Inc.), a Certified Public Accountant in Marietta, has
approached your construction management firm requesting a feasibility study that
includes a plan for construction activities that need to be completed by the start of the
Spring semester. After meeting with your shareholders to determine whether or not it is in
the company's best interest to go after this work for these particular people, you decide
that it is worth the risk. During a preconstruction meeting, the project team develops
activities and duration estimates that will drive the schedule, and provide enough
information to the owner of your company to make a decision. The transcript from the
meeting is on Page 3. These steps are the deliverables required for the midterm. After
reading the transcript, complete the steps, in order, and answer the questions below. Step
1- Develop a dependency table showing activity relationships Step 2- Layout an AON
network diagram, and develop a legend or key for each activity box. Step 3-Perform a
Forward Pass, Backward Pass, and Float Calculation and clearly indicate the critical path
with color or highlighting. Remember, a clear presentation to the owner (that's me) is
crucial! This should be done by hand only. Use the fully constructed AON network diagram
(steps 1-3 above) indicating the critical path, (a calendar with dates is useful to reference,
but not a required deliverable) to answer the following questions:
a. What activities make up the critical path?
b. When is the proposed finish date?
c. What are two near-critical activities?
2 d. If the Architect changes their mind, and the exterior siding material is delayed and does
not arrive until Wednesday, November 6, 2024, causing this to be the earliest starting date
for the activity, does this impact the finish date listed in question b.? How do you know?
e. What is the new revised finish date if the carpenters that are responsible for the exterior
siding cannot work the week of the 4th of November, assuming the material is delayed, and
could only start back on Tuesday, November 12th? How do you know? f. If the insulation
material is delayed and does not arrive until Tuesday, November 12th, 2024, causing this to
be the earliest starting date for the activity, does this impact the finish date listed in
question b.? (ignore previous delays in questions d. and e.) How do you know? g. What is
the new revised finish date if the insulators cannot work the week of the 11th of November,
assuming material is delayed, and could only start back on Monday, November 18th? How
do you know? h. If the Rough Electric takes 4 additional workdays, does this impact the
overall project? If so, by how many days? (ignore d. through g.) . If Dr. Moore and Dr. Al-
Shenawa want to visit the jobsite on Thursday, November 21st, and the day after to play
golf with Bubba, and it shuts down all work for both days because Bubba is a big hitter and
everybody wants to watch, which activities will be impacted? (ignore d. through h.)
Transcribed Image Text:Bee, Andrew& Al Shanawa (MGA, Inc.), a Certified Public Accountant in Marietta, has approached your construction management firm requesting a feasibility study that includes a plan for construction activities that need to be completed by the start of the Spring semester. After meeting with your shareholders to determine whether or not it is in the company's best interest to go after this work for these particular people, you decide that it is worth the risk. During a preconstruction meeting, the project team develops activities and duration estimates that will drive the schedule, and provide enough information to the owner of your company to make a decision. The transcript from the meeting is on Page 3. These steps are the deliverables required for the midterm. After reading the transcript, complete the steps, in order, and answer the questions below. Step 1- Develop a dependency table showing activity relationships Step 2- Layout an AON network diagram, and develop a legend or key for each activity box. Step 3-Perform a Forward Pass, Backward Pass, and Float Calculation and clearly indicate the critical path with color or highlighting. Remember, a clear presentation to the owner (that's me) is crucial! This should be done by hand only. Use the fully constructed AON network diagram (steps 1-3 above) indicating the critical path, (a calendar with dates is useful to reference, but not a required deliverable) to answer the following questions: a. What activities make up the critical path? b. When is the proposed finish date? c. What are two near-critical activities? 2 d. If the Architect changes their mind, and the exterior siding material is delayed and does not arrive until Wednesday, November 6, 2024, causing this to be the earliest starting date for the activity, does this impact the finish date listed in question b.? How do you know? e. What is the new revised finish date if the carpenters that are responsible for the exterior siding cannot work the week of the 4th of November, assuming the material is delayed, and could only start back on Tuesday, November 12th? How do you know? f. If the insulation material is delayed and does not arrive until Tuesday, November 12th, 2024, causing this to be the earliest starting date for the activity, does this impact the finish date listed in question b.? (ignore previous delays in questions d. and e.) How do you know? g. What is the new revised finish date if the insulators cannot work the week of the 11th of November, assuming material is delayed, and could only start back on Monday, November 18th? How do you know? h. If the Rough Electric takes 4 additional workdays, does this impact the overall project? If so, by how many days? (ignore d. through g.) . If Dr. Moore and Dr. Al- Shenawa want to visit the jobsite on Thursday, November 21st, and the day after to play golf with Bubba, and it shuts down all work for both days because Bubba is a big hitter and everybody wants to watch, which activities will be impacted? (ignore d. through h.)
Transcript "Alright. We need to start immediately, no time for delay. Use Monday
September 30, 2024, as a starting point" "Bossman, do we need to work weekends and
holidays to knock this thing out? I have some things planned for the weekends coming up
and Thanksgiving." "No, we don't need to extend resources for that. No weekends or
holidays, standard 5 day work week should do it. Well, we will certainly have to start with
SITEWORK, and this will take 4 days probably" "After that, the UNDERGROUND UTILITIES
can start, and I know we can knock those out in 12 days" "Since we are talking about the
outside work, we would have to include 4 days for LANDSCAPING before we CLOSEOUT
THE PROJECT" "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is
complete" "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!"
"How much time will we need for EXTERIOR PAINTING?" "5 days" "Okay, but we will have to
complete the EXTERIOR SIDING and FINISH ROOF before then" "Yep, but let's get back to
the beginning. The ROUGH PLUMBING should take 12 days, and needs to start 5 days after
FORM/POUR SLAB starts, which will take at least 7 days to complete" "Do we have to wait
until the UNDERGROUND UTILITIES are complete before we FORM/POUR SLAB?" "No,
FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is
complete before starting to FRAME WALLS" "FRAME WALLS is crucial, let's put 5 days for
that. Its completion allow ROUGH ELECTRIC, FRAME ROOF, and the WINDOWS/DOORS to
start" "Okay, so let's say 7 days for ROUGH ELECTRIC, 10 days to hang WINDOWS/DOORS
and the carpenters can FRAME ROOF in 7 days" "If the boys can frame the roof in 7 days,
surely the roofers can FINISH ROOF right after that in 3 days as well" "Yep, FRAME ROOF
will allow ROUGH MECHANICAL to start, which will take every bit of 5 days. ROUGH
MECHANICAL cannot start until the UNDERGROUND UTILITIES are done either" "EXTERIOR
SIDING can start after the WINDOWS/DOORS, and should take 5 days to complete" "Slow
down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH
MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF
firstbefore DRYWALL starts this time!" "10-4 Boss" "INSULATION might take 3 days, but
needs to wait on ROUGH ELECTRIC, ROUGH MECHANICAL, and ROUGH PLUMBING to be
complete before starting, but should be complete before DRYWALL is complete " "We need
to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND UTILITIES"
"Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING,
and FINISH MECHANICAL, and know that all three need DRYWALL to be complete before
starting" "Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete,
and needs to happen after DRYWALL and before FINISH ELECTRIC" "That should do
it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3 FINISH MEP activities
and LANDSCAPING to tie up any loose ends" "Sounds good. Great work boys!"|
Transcribed Image Text:Transcript "Alright. We need to start immediately, no time for delay. Use Monday September 30, 2024, as a starting point" "Bossman, do we need to work weekends and holidays to knock this thing out? I have some things planned for the weekends coming up and Thanksgiving." "No, we don't need to extend resources for that. No weekends or holidays, standard 5 day work week should do it. Well, we will certainly have to start with SITEWORK, and this will take 4 days probably" "After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in 12 days" "Since we are talking about the outside work, we would have to include 4 days for LANDSCAPING before we CLOSEOUT THE PROJECT" "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete" "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!" "How much time will we need for EXTERIOR PAINTING?" "5 days" "Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then" "Yep, but let's get back to the beginning. The ROUGH PLUMBING should take 12 days, and needs to start 5 days after FORM/POUR SLAB starts, which will take at least 7 days to complete" "Do we have to wait until the UNDERGROUND UTILITIES are complete before we FORM/POUR SLAB?" "No, FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is complete before starting to FRAME WALLS" "FRAME WALLS is crucial, let's put 5 days for that. Its completion allow ROUGH ELECTRIC, FRAME ROOF, and the WINDOWS/DOORS to start" "Okay, so let's say 7 days for ROUGH ELECTRIC, 10 days to hang WINDOWS/DOORS and the carpenters can FRAME ROOF in 7 days" "If the boys can frame the roof in 7 days, surely the roofers can FINISH ROOF right after that in 3 days as well" "Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of 5 days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done either" "EXTERIOR SIDING can start after the WINDOWS/DOORS, and should take 5 days to complete" "Slow down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF firstbefore DRYWALL starts this time!" "10-4 Boss" "INSULATION might take 3 days, but needs to wait on ROUGH ELECTRIC, ROUGH MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be complete before DRYWALL is complete " "We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND UTILITIES" "Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING, and FINISH MECHANICAL, and know that all three need DRYWALL to be complete before starting" "Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete, and needs to happen after DRYWALL and before FINISH ELECTRIC" "That should do it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3 FINISH MEP activities and LANDSCAPING to tie up any loose ends" "Sounds good. Great work boys!"|
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning