BEC pho is a company that manufactures turbines for power generating plams. BEC recently signed a contract with an independent power producer, Motlakase. According to the contract, BEC agreed to supply a turbine for a Start in the contract rate of 100 megawatts. new power plant owned by Motlakage. BEC guaranteed that the turbine would produce electricity at a In addition to supplying the turbine. BEC's contractual responsibilities included providing technical advice and on-site support during the up, testing and commissioning of the turbine. Motlakase hired Modupi, plant including installing the turbine supplied by BEC.. Modupi Installed the turbine and the construction of the power plant is now almost complete. The contractor is now ready to commission the plant by running a number of tests to make a separate construction contractor, to construct power sure that the turbine is working properly and producing the power at the guaranted rate. years. BEC sent one of its employees, Thabo, to the site to witness the tests and to provide technical advice to assist Modupi cluring the testing, Thabo is a very experienced professional engineer and has worked on many different construction sites over the Soon after arriving at the site, it become apparent to Thabo that Modupi was carying out its work In an unsafe manner. Many of Modupi's workers were working without hardhats, eye protection and fact, Thabo learn t that Modupi had not established any safety procectures for it's crew- safety shoes. In Mocupi completed the tests. However, during testing, Thabo noticed that Modopi's personnel did not conduct the teats in complete Compliance with the official teuting procedures that were established for the project. According to the tests that were actually carried out, it seemed that the turbine achieved the guaranted rate of performance THI sophi In power at 96 megawat properly, they would reality, however, the turbines only produced Thabo realized that had the tests been conducted have revealed the turbine's deficient power output. Thabo was concerned that BEC would be required under its contract to Motlarase liquidated damages as a result of power deficience. Thabo did not say anything to anyone about the improper testing procedure. No one else noticed that the tests were not performed properly. pay The circumstances actions of Thabo include the following Observing but not reporting the unsafe conditions under which the employees of Modupi are working, and Observing that the tests being conducted by Mudupi were not In Complete compliance with the official testing procedures established for the pigect a) what duties, if any does Thabo have under the code of ethices and the definition of professional misconduct regarding the potential dangers to Mocupi 's workers b) Explain whethe. I matters to Thabo's duties that the unsafe practices involved work that was no relevant to the sowices that BEC was hired to perform and whether it matters to Thabo's Modupi agreed to have overall responsibility duties that for site safety c) Comment on Thabo's obligations, if any, under the code of ethics definition of professional misconduct regarding the test. and procedure and the failure of the turbine to perform at the guaranted. (in your answer, assume that the imprope, testing and deficient noks power out Put create no safety inst rate? or other dangerous situation ด Π R

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
BEC
pho
is a company that manufactures turbines for power generating
plams. BEC recently signed a contract with an independent power producer,
Motlakase. According to the contract, BEC agreed to supply a turbine for a
Start
in the contract
rate of 100 megawatts.
new power plant owned by Motlakage. BEC guaranteed
that the turbine would produce electricity at a
In addition to supplying the turbine. BEC's contractual responsibilities
included providing technical advice and on-site support during the
up, testing and commissioning of the turbine. Motlakase
hired Modupi,
plant including installing the turbine supplied by BEC.. Modupi Installed
the turbine and the construction of the power plant is now almost
complete. The contractor is now ready to commission the plant by
running a number of tests to make
a separate construction contractor, to construct power
sure that the turbine is working
properly and producing the power at the guaranted rate.
years.
BEC sent one of its employees, Thabo, to the site to witness the tests
and to provide technical advice to assist Modupi cluring the testing,
Thabo is a very experienced professional engineer and has worked on many
different construction sites over the Soon after arriving at the
site, it become apparent to Thabo that Modupi was carying out its work
In an unsafe manner. Many of Modupi's workers were working
without hardhats, eye protection and
fact, Thabo learn t
that Modupi had not established any safety procectures for it's crew-
safety
shoes. In
Mocupi completed the tests. However, during testing, Thabo noticed
that Modopi's personnel did not conduct the teats in complete
Compliance with the official teuting procedures that were established
for the project. According to the tests that were actually carried out, it
seemed that the turbine achieved the guaranted rate of performance
Transcribed Image Text:BEC pho is a company that manufactures turbines for power generating plams. BEC recently signed a contract with an independent power producer, Motlakase. According to the contract, BEC agreed to supply a turbine for a Start in the contract rate of 100 megawatts. new power plant owned by Motlakage. BEC guaranteed that the turbine would produce electricity at a In addition to supplying the turbine. BEC's contractual responsibilities included providing technical advice and on-site support during the up, testing and commissioning of the turbine. Motlakase hired Modupi, plant including installing the turbine supplied by BEC.. Modupi Installed the turbine and the construction of the power plant is now almost complete. The contractor is now ready to commission the plant by running a number of tests to make a separate construction contractor, to construct power sure that the turbine is working properly and producing the power at the guaranted rate. years. BEC sent one of its employees, Thabo, to the site to witness the tests and to provide technical advice to assist Modupi cluring the testing, Thabo is a very experienced professional engineer and has worked on many different construction sites over the Soon after arriving at the site, it become apparent to Thabo that Modupi was carying out its work In an unsafe manner. Many of Modupi's workers were working without hardhats, eye protection and fact, Thabo learn t that Modupi had not established any safety procectures for it's crew- safety shoes. In Mocupi completed the tests. However, during testing, Thabo noticed that Modopi's personnel did not conduct the teats in complete Compliance with the official teuting procedures that were established for the project. According to the tests that were actually carried out, it seemed that the turbine achieved the guaranted rate of performance
THI
sophi
In
power at 96 megawat
properly, they would
reality, however, the turbines only produced
Thabo realized that had the tests been conducted
have revealed the turbine's deficient power output. Thabo was
concerned that BEC would be required under its contract to
Motlarase liquidated damages as a result of power deficience. Thabo
did not say anything to anyone about the improper testing procedure.
No one else noticed that the tests were not performed properly.
pay
The circumstances actions of Thabo include the following
Observing but not reporting the unsafe conditions under which the
employees of Modupi are working, and
Observing that the tests being conducted
by
Mudupi were not
In Complete compliance with the official testing procedures established
for the pigect
a) what duties, if any does Thabo have under the code of ethices
and the definition of professional misconduct regarding the potential
dangers to Mocupi 's workers
b) Explain whethe. I matters to Thabo's duties that the unsafe
practices involved work that was no relevant to the sowices
that BEC was hired to perform and whether it matters to Thabo's
Modupi agreed to have overall responsibility
duties that
for site safety
c) Comment on Thabo's obligations, if any, under the code of ethics
definition of professional misconduct regarding the test.
and
procedure and the failure of the turbine to perform at
the guaranted.
(in your answer, assume that the imprope, testing and deficient
noks
power out
Put create no safety inst
rate?
or other dangerous situation
ด
Π
R
Transcribed Image Text:THI sophi In power at 96 megawat properly, they would reality, however, the turbines only produced Thabo realized that had the tests been conducted have revealed the turbine's deficient power output. Thabo was concerned that BEC would be required under its contract to Motlarase liquidated damages as a result of power deficience. Thabo did not say anything to anyone about the improper testing procedure. No one else noticed that the tests were not performed properly. pay The circumstances actions of Thabo include the following Observing but not reporting the unsafe conditions under which the employees of Modupi are working, and Observing that the tests being conducted by Mudupi were not In Complete compliance with the official testing procedures established for the pigect a) what duties, if any does Thabo have under the code of ethices and the definition of professional misconduct regarding the potential dangers to Mocupi 's workers b) Explain whethe. I matters to Thabo's duties that the unsafe practices involved work that was no relevant to the sowices that BEC was hired to perform and whether it matters to Thabo's Modupi agreed to have overall responsibility duties that for site safety c) Comment on Thabo's obligations, if any, under the code of ethics definition of professional misconduct regarding the test. and procedure and the failure of the turbine to perform at the guaranted. (in your answer, assume that the imprope, testing and deficient noks power out Put create no safety inst rate? or other dangerous situation ด Π R
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning