Balboa Industries’ Electronics Division is trying to reduce supply chain risk by making more responsible make/buy decisions through improved cost estimation. A high-use component (expected usage is 5000 units per year) can be purchased for $25 per unit with delivery promised within a week. Alternatively, Balboa can make the component inhouse and have it readily available at a cost of $5 per unit, if equipment costing $150,000 is purchased. Labor and other operating costs are estimated to be $35,000 per year over the study period of 5 years. Salvage is estimated at 10% offirst cost and i = 12% per year. Neglecting the element of availability (a) determine the breakeven quantity, and (b) recommend making or buying atthe expected usage level.
Balboa Industries’ Electronics Division is trying to reduce supply chain risk by making more responsible make/buy decisions through improved cost estimation. A high-use component (expected usage is 5000 units per year) can be purchased for $25 per unit with delivery promised within a week. Alternatively, Balboa can make the component inhouse and have it readily available at a cost of $5 per unit, if equipment costing $150,000 is purchased. Labor and other operating costs are estimated to be $35,000 per year over the study period of 5 years. Salvage is estimated at 10% of
first cost and i = 12% per year. Neglecting the element of availability (a) determine the breakeven quantity, and (b) recommend making or buying at
the expected usage level.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps