Question

please solve all parts within 30 minutes.

The following activities are part of a project to be
scheduled using CPM:
ACTIVITY IMMEDIATE
A
B
C
D
E
TI
G
PREDECESSOR
A
A
с
B
D
D
EE
b. What is the critical path?
TIME
(WEEKS)
4
5
3
9
8
3
5
multiple choice
A-C-D-E-G
A-B-E-G
A-C-D-F-G
A-B-D-F-G
c. How many weeks will it take to complete the
project?
d. How much slack does activity B have?
Transcribed Image Text:The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE A B C D E TI G PREDECESSOR A A с B D D EE b. What is the critical path? TIME (WEEKS) 4 5 3 9 8 3 5 multiple choice A-C-D-E-G A-B-E-G A-C-D-F-G A-B-D-F-G c. How many weeks will it take to complete the project? d. How much slack does activity B have?
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.