An order for 100 of a product is processed on work centers A and B. The setup time on A is 30 minutes, and run time is 10 minutes per piece. The setup time on B is 50 minutes, and the run time is 5 minutes per piece. Wait time between the two operations is 4 hours. The move time between A and B is 10 minutes. Wait time after operation B is 4 hours, and the move time into stores is 15 minutes. There is no queue at either workstation. If it is decided to overlap operations A and B by splitting the lot of 100 into two lots of 70 and 30. Wait time between A and B and between B and stores is eliminated. Setup on operation B can start before the first batch arrives. Calculate the manufacturing lead time for the whole order. Calculate the manufacturing lead time for the first patch.
An order for 100 of a product is processed on work centers A and B. The setup time on A is 30 minutes, and run time is 10 minutes per piece. The setup time on B is 50 minutes, and the run time is 5 minutes per piece. Wait time between the two operations is 4 hours. The move time between A and B is 10 minutes. Wait time after operation B is 4 hours, and the move time into stores is 15 minutes. There is no queue at either workstation.
If it is decided to overlap operations A and B by splitting the lot of 100 into two lots of 70 and 30. Wait time between A and B and between B and stores is eliminated.
Setup on operation B can start before the first batch arrives.
- Calculate the manufacturing lead time for the whole order.
- Calculate the manufacturing lead time for the first patch.