Adirondack Paper Mills, Inc. operates paper plants in Augusta, Maine, and Tupper Lake, New York. Warehouse facilities are located in Albany, New York, and Portsmouth, New Hampshire. Distributors are located in Boston, New York, and Philadelphia. The Augusta plant has a capacity of 300 units and the Tupper Lake plant has a capacity of 100 units. Boston has a demand of 150 units, New York has a demand of 100 units, and Philadelphia has a demand of 150 units. The unit transportation costs (in dollars) for shipments from the two plants to the two warehouses are presented in Table 4 and those from the two warehouses to the three distributors are presented in Table 5. Table 4: Problem 1.10a Plant/Warehouse Albany Portsmouth Augusta 7 5 Tupper Lake 3 4 Table 5: Problem 1.10b Warehouse/Distributor Boston New York Philadelphia Albany 8 5 7 Portsmouth 5 6 10 a. Draw the network representation of the Adirondack Paper Mills problem. b. Formulate the Adirondack Paper Mills problem as a linear programming problem. c. Solve the linear program to determine the minimum cost shipping schedule for the problem.
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Adirondack Paper Mills, Inc. operates paper plants in Augusta, Maine, and
Tupper Lake, New York. Warehouse facilities are located in Albany, New York, and Portsmouth, New Hampshire. Distributors are located in Boston, New York, and Philadelphia. The Augusta plant has a capacity of 300 units and the Tupper Lake plant has a capacity of 100 units. Boston has a demand of 150 units, New York has a demand of 100 units, and Philadelphia has a demand of 150 units. The unit transportation costs (in dollars) for shipments from the two plants to the two warehouses are presented in Table 4 and those from the two warehouses to the three
distributors are presented in Table 5.
Table 4: Problem 1.10a
Plant/Warehouse Albany Portsmouth
Augusta 7 5
Tupper Lake 3 4
Table 5: Problem 1.10b
Warehouse/Distributor Boston New York Philadelphia
Albany 8 5 7
Portsmouth 5 6 10
a. Draw the network representation of the Adirondack Paper Mills problem.
b. Formulate the Adirondack Paper Mills problem as a linear programming
problem.
c. Solve the linear program to determine the minimum cost shipping
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 6 images