b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity (days) A B C D E F G Activity Activity Time (days) Immediate Predecessor(s) The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: a. Choose the correct network diagram for this project. A. OC. Start E PO 6 B2 F3 95 AT Start 7 B2 G 98 8 E3 D 95 Finish F 6 G 8 2 ABCDEFG Finish 7245360 8 B. |< < B, C DEE Q B2 F 2 6 °.. Start AT D 7 5 9-6 E Finish 3 C 8 CB G 2 B2 F 6 Start E3 95 Finish LY LY Activity Slack (days) A b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) BCDE G Clear all

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Can you help me with part C. Parts A and B are correct. 

b. Determine the critical path and project duration.
The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.)
c. Calculate the slack for each activity. (Enter your responses as integers.)
Slack
Activity
(days)
A
B
C
D
E
F
G
Transcribed Image Text:b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity (days) A B C D E F G
Activity
Activity Time (days)
Immediate Predecessor(s)
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel:
a. Choose the correct network diagram for this project.
A.
OC.
Start
E
PO
6
B2
F3
95
AT
Start
7
B2
G
98
8
E3
D
95
Finish
F
6
G
8
2
ABCDEFG
Finish
7245360
8
B.
|< <
B, C
DEE
Q
B2
F
2
6
°..
Start
AT
D
7
5
9-6
E
Finish
3
C
8
CB
G
2
B2
F
6
Start
E3
95
Finish
LY
LY
Activity
Slack
(days)
A
b. Determine the critical path and project duration.
The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.)
c. Calculate the slack for each activity. (Enter your responses as integers.)
BCDE
G
Clear all
Transcribed Image Text:Activity Activity Time (days) Immediate Predecessor(s) The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: a. Choose the correct network diagram for this project. A. OC. Start E PO 6 B2 F3 95 AT Start 7 B2 G 98 8 E3 D 95 Finish F 6 G 8 2 ABCDEFG Finish 7245360 8 B. |< < B, C DEE Q B2 F 2 6 °.. Start AT D 7 5 9-6 E Finish 3 C 8 CB G 2 B2 F 6 Start E3 95 Finish LY LY Activity Slack (days) A b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) BCDE G Clear all
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.