a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign. NPV: $ IRR: MIRR The project's payback: years b. Assume management is unsure about the $110,000 cost savings this figure could deviate by as much as plus or minus 20%. Do not round intermediate calculations. Round your answer to the nearest dollar. Negative values, if any, should be indicated by a minus sign. Calculate the NPV if cost savings value deviate by plus 20%. $ Calculate the NPV if cost savings value deviate by minus 20%.

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
icon
Concept explainers
Topic Video
Question
Calculate the NPV if cost savings value deviate by minus 20%.
$
c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine's salvage value, and the working capital (WC)
requirement. She asks you to use the following probabilities and values in the scenario analysis:
Scenario
Worst case
Base case
Best case
Probability Cost Savings Salvage Value
0.35
$ 88,000
$28,000
0.35
0.30
110,000
132,000
33,000
38,000
WC
$40,000
35,000
30,000
Calculate the project's expected NPV, its standard deviation, and its coefficient of variation. Do not round intermediate calculations. Round the monetary values to
the nearest dollar and a coefficient of variation to two decimal places. Negative values, if any, should be indicated by a minus sign.
The project's expected NPV: $
Standard deviation: $
Coefficient of variation:
Transcribed Image Text:Calculate the NPV if cost savings value deviate by minus 20%. $ c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine's salvage value, and the working capital (WC) requirement. She asks you to use the following probabilities and values in the scenario analysis: Scenario Worst case Base case Best case Probability Cost Savings Salvage Value 0.35 $ 88,000 $28,000 0.35 0.30 110,000 132,000 33,000 38,000 WC $40,000 35,000 30,000 Calculate the project's expected NPV, its standard deviation, and its coefficient of variation. Do not round intermediate calculations. Round the monetary values to the nearest dollar and a coefficient of variation to two decimal places. Negative values, if any, should be indicated by a minus sign. The project's expected NPV: $ Standard deviation: $ Coefficient of variation:
Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3-
year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable
depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5-
year life. Madison's marginal tax rate is 25%, and a 14% cost of capital is appropriate for the project.
a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage
values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign.
NPV: S
IRR:
%
$
%
MIRR:
The project's payback:
years
b. Assume management is unsure about the $110,000 cost savings this figure could deviate by as much as plus or minus 20%. Do not round intermediate
calculations. Round your answer to the nearest dollar. Negative values, if any, should be indicated by a minus sign.
Calculate the NPV if cost savings value deviate by plus 20%.
Calculate the NPV if cost savings value deviate by minus 20%.
Transcribed Image Text:Madison Manufacturing is considering a new machine that costs $350,000 and would reduce pre-tax manufacturing costs by $110,000 annually. Madison would use the 3- year MACRS method to depreciate the machine, and management thinks the machine would have a value of $33,000 at the end of its 5-year operating life. The applicable depreciation rates are 33.33%, 44.45%, 14.81%, and 7.41%. Working capital would increase by $35,000 initially, but it would be recovered at the end of the project's 5- year life. Madison's marginal tax rate is 25%, and a 14% cost of capital is appropriate for the project. a. Calculate the project's NPV, IRR, MIRR, and payback. Do not round intermediate calculations. Round the monetary value to the nearest dollar and percentage values and payback to two decimal places. Negative values, if any, should be indicated by a minus sign. NPV: S IRR: % $ % MIRR: The project's payback: years b. Assume management is unsure about the $110,000 cost savings this figure could deviate by as much as plus or minus 20%. Do not round intermediate calculations. Round your answer to the nearest dollar. Negative values, if any, should be indicated by a minus sign. Calculate the NPV if cost savings value deviate by plus 20%. Calculate the NPV if cost savings value deviate by minus 20%.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 8 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education