(a) Which activities form the critical path? (b) What is the estimated time of the critical path? (c) What are the project variance and the project standard deviation?
(a) Which activities form the critical path? (b) What is the estimated time of the critical path? (c) What are the project variance and the project standard deviation?
Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
Related questions
Question
(a) Which activities form the critical path?
(b) What is the estimated time of the critical path?
(c) What are the project variance and the project standard deviation?
(d) What is the probability of completion of the project before week 42?

Transcribed Image Text:Optimistic Probable Pessimistic Expected
Activity Preceding
Variance
Time
Time
Time
Time
A
--
7
10
19
11
4
B
A
2
2
8
3
1
C
A
8
12
16
12
1.78
D
A
E
B
34
5
10
5.5
1.36
6
8
6
0.44
F
B
G
C, F
H
D
622
8
10
8
0.44
32
4
3
0.11
8
3
1
|
H
J
G, I
79
6
00
8
16
9
2.78
4
CO
6
14
7
2.78
K
E, J
2
LO
8
5
1
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 9 images

Recommended textbooks for you

Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated

Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education

Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY

Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated

Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education

Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY

Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,