a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is (assume that jobs came in the order in which they are listed in the table): Sequence 1 2 3 لا 4 5 Job A B C D E The average tardiness (job lateness) for the sequence developed using the FCFS rule = days (round your response to two decimal places).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the
order is (assume that jobs came in the order in which they are listed in the table):
Sequence
1
2
3
4
5
Job
A
B
C
D
E
The average tardiness (job lateness) for the sequence developed using the FCFS rule =
days (round your response to two decimal places).
The following jobs are waiting to be processed at the same machine center. Jobs
are logged as they arrive:
Job
ABCDE
Due Date
315
313
312
325
314
Duration (days)
3
8
16
5
All dates are specified as manufacturing planning calendar days. Assume that all
jobs arrive on day 275. Assume each job starts at the beginning of the day and
finishes at the end of the day (a job that begins on day 275 and takes 8 days will
finish on day 282, and the next job begins in the morning of day 283). Compute all
times based on initiating work on day 275.
Transcribed Image Text:a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is (assume that jobs came in the order in which they are listed in the table): Sequence 1 2 3 4 5 Job A B C D E The average tardiness (job lateness) for the sequence developed using the FCFS rule = days (round your response to two decimal places). The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: Job ABCDE Due Date 315 313 312 325 314 Duration (days) 3 8 16 5 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day (a job that begins on day 275 and takes 8 days will finish on day 282, and the next job begins in the morning of day 283). Compute all times based on initiating work on day 275.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.