A UAE based company of Solar Panel supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June and cost information are presented in the tables fand 2 below. Use Plan 2-by using subcontractors with constant workforce at lowest demand per day and calculate Total Cost of the Plan Table 1 PRODUCTION DAYS DEMAND DE MAND FORECAST PER DAY 1.073 16 903 21 1,000 24 1,000 24 1,272 22 1,368 29 $ per unit 95 per hour (Working hours per day) 1.6 hours per unit MONTH Jan Feb Mar Apr May June Table 2 Cost Information Subcontracting cost per unit Average pay rate Labor hours to produce a unt

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
A UAE based company of Solar Panel supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June and cost information are presented in the
tables 1and 2 below. Use Plan 2-by using subcontractors with constant workforce at lowest demand per day and calculate Total Cost of the Plan.
Table 1
PRODUCTION DEMAND
DAYS
FORECAST
DEMAND
PER DAY
22
1,073
18
903
1,000
1,000
1,272
1,388
29 $ per unit
95 per hour ( Working hours per day)
1.6 hours per unit
MONTH
Jan
Feb
Mar
Apr
May
June
Table 2
Cost Information
Subcontracting cost per unit
Average pay rate
Labor-hours to produce a unt
21
24
24
22
2
Transcribed Image Text:A UAE based company of Solar Panel supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June and cost information are presented in the tables 1and 2 below. Use Plan 2-by using subcontractors with constant workforce at lowest demand per day and calculate Total Cost of the Plan. Table 1 PRODUCTION DEMAND DAYS FORECAST DEMAND PER DAY 22 1,073 18 903 1,000 1,000 1,272 1,388 29 $ per unit 95 per hour ( Working hours per day) 1.6 hours per unit MONTH Jan Feb Mar Apr May June Table 2 Cost Information Subcontracting cost per unit Average pay rate Labor-hours to produce a unt 21 24 24 22 2
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Cost estimation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education