A survey monument is to be installed at STA 12+55.25’. The reclamation district is installing a new sewer manhole at that location and the monument needs to be moved 177 inches further down the center line (increasing station #). What is the new station of the monument?
A survey monument is to be installed at STA 12+55.25’. The reclamation district is installing a new sewer manhole at that location and the monument needs to be moved 177 inches further down the center line (increasing station #). What is the new station of the monument?
Construction Materials, Methods and Techniques (MindTap Course List)
4th Edition
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:William P. Spence, Eva Kultermann
Chapter4: The Building Site
Section: Chapter Questions
Problem 3RQ
Related questions
Question
A
Expert Solution
Step 1
Given:
Current Station = STA 12+55.25’
Increase in station = 177 in
Step 2
In the numbering of a station, STA stands for station and each station is at a distance of 100’ from each other. So, the number of a station represents that by what multiple of 100’ it is away from the benchmark. Also, the numbers after the plus sign shows by how much further down in ft you have moved from the station.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning