A solid circular steel shaft is encased in a copper hollow shaft so as to make a compound shaft. The diameter of the steel shaft is 8 cm, and the outer diameter of the copper shaft is 11 cm. The compound shaft, of length 200 cm, is subjected to an axial torque of 8 kNm. Determine: (a) Maximum shear stress in steel and copper. (b) Angular twist per unit length. Given; G 2G - 80 kN / mm
Q: Drummond’s standard quantities for 1 unit of product include 2 pounds of materials and 1.5 labor…
A: Standard costs are estimates of the actual costs in a company's production process, because actual…
Q: Organics Corporation uses two different types of labor to manufacture its product. The types of…
A: Labor mix variance :— It is the difference between Revised Standard hours at Standard rate and…
Q: a. Prepare a materials variance information table showing the standard price, the actual price, the…
A: Generally, a variance refers to the difference between an expected, budgeted or planned value and an…
Q: Required: 1. Suppose Keller uses a traditional costing system with machine hours as the cost driver.…
A: The pre-determined overhead rate is calculated as the estimated overhead costs divided by the…
Q: Works overhead is Rs 40,000, total machine hours is 8500 hours and time allowed for machine setting…
A: We have the following information: Work overhead is Rs.40,000 Total machine hours: 8,500 hours Time…
Q: Third: Raw materials and Purchases: Quantity needed from material "M": "E" 17 kg. "F" 13 kg. "G"…
A: To prepare the marketing budget and administrative budget, we need to gather the relevant costs from…
Q: Oakwood Creations Company makes decorative candle pedestals. An industrial engineer consultant…
A: Direct labor cost is calculated by multiplying direct labor hours by direct labor rate. Direct labor…
Q: One of the chemical fertilizers produced by Ozone Chemicals passes two processes. In Process 1,…
A: …
Q: materials (fiberglas labor le manufacturing ovex ed on direct labor ho manufacturing overhea .000 +…
A: A journal entry is used to record day-to-day transactions of the business by debiting and crediting…
Q: Pothos manufactures two components A & B. There are to be 3,000 of unit A and 4,000 of unit B…
A: Optimum mix method of production will be used when a factor which essential for production is…
Q: 3 kilos at RM 5 per kilo 2 hours at RM 5 per hour RM 5 per labour hour RM 6 per labour hour heen…
A: Absorption costing refers to the process of estimating the cost of a product on the basis of its…
Q: Becton Labs, Incorporated, produces various chemical compounds for industrial use. One compound,…
A: Variance analysisVariance analysis is an analysis of a difference between planned and actual…
Q: Chan Company identified the following budgeted data for this year. The company manufactures two…
A: The plantwide overhead rate is calculated by dividing the total budgeted overhead cost by the total…
Q: ASAP In the production of a certain product, two operation are available. One willproduce 40 units…
A: The Break-even point refers to the level at which the cost of production is equal to the total…
Q: In the Forming Department, the variable overheads is £200,900 and the fixed overheads is £401,800.…
A: Overhead is the indirect costs a business incurs in its operations, such as rent, utilities, and…
Q: Vernon Inc. has analyzed the setup time on its computer-controlled lathe. The setup requireschanging…
A: Improving resource usage has numerous advantages for the organization and process.Shorter lead…
Q: s, the theoretical minimum number of workstations
A: We can solve the given question ysing network diagrams. Also, theoritical minimum number of…
Q: Bonita's standard quantities for 1 unit of product include 3 pounds of materials and 2.5 labor…
A: The product cost comprises materials, labor and overhead cost. The standard cost is based on…
Q: Huron Company produces a commercial cleaning compound known as Zoom. The direct materials and direct…
A:
Q: The Splash makes large fiberglass swimming pools and uses machine hours and direct labor hours to…
A: Production overhead is the amount spent on indirect expenses in the production activities. Under the…
Q: Sunland Irrigation, Inc. is known throughout the world for its H2O-X high-capacity water pump, used…
A: Variance analysis shows the difference between budgeted costs and the actual costs.
Q: Northern Defense manufactures radar systems. It has just completed the manufacture of its first…
A: A learning curve is the representation in graph form of the rate of learning something over time or…
Q: The following standard costs were developed for one of the products of ELJAY Sdn Bhd (ESB): STANDARD…
A: Overhead Cost Variance is divided into 2 parts: Variable Overhead Cost Variance Fixed Overhead Cost…
Q: West Partners manufactures metal fixtures. Each fitting requires both steel and an alloy that can…
A: Note :Budget is an operating and financial plan.Budgeting means preparing budgets. It is the process…
Q: Life Force Fitness, Inc., assembles and sells treadmills. Activity-based product information for…
A: Activity based costing is a technique which is used for allocating the overhead rates to the…
Q: The following information is available for Night Raid Company for the current year: Standard:…
A: Labor rate variance:— It is the difference between actual labor hours at standard rate and actual…
Q: Landkirk computes its overhead rates using practical volume, which is 3,400 units. The actual…
A: ''Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: A cement grinding mill "X" with a capacity of 48.072 tons per hour utilizes forged steel grinding…
A: Total cost refers to the overall costs that are incurred for producing the desired output in a…
Q: Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present…
A: Answer:- Formulas: 1. Value-added processing time= Process step1 + Process step 2 + Process step 3…
Q: Oakwood Creations Company makes decorative candle pedestals. An industrial engineer consultant…
A: Direct labor cost is calculated by multiplying direct labor hours by direct labor rate. Direct labor…
Q: Hernandez Corp. wants to compute its throughput for August. The following production data are…
A: Manufacturing cycle efficiency is calculated by dividing value added time by the total processing…
Q: Oakwood Creations Company makes decorative candle pedestals. An industrial engineer consultant…
A: Direct costs are the expenses that are directly used for the production of goods and services for…
Q: Imperial Jewelers manufactures and sells a gold bracelet for $409.00. The company's accounting…
A: Variable costs are those costs which change along with changes in activity levels. Fixed costs do…
Q: Required: a. Prepare a production budget for the coming year. b. Estimate the direct materials,…
A: Estimated units to be produced 87000 Total direct material cost 1969680 Total labor…
Q: In certain cases, experience will indicate the best time to perform certain operations to maintain…
A: Answer - Part 1 - Calculation of Cost per piece - ( 200 pieces) Particular Amount Piece…
Q: Calculate the labour price and usage variance, and the labour cost variance for the concrete work.
A: Labour cost variance is the difference between standard cost and actual cost of labour. This can be…
Q: Choi Company manufactures two skin care lotions, Smooth Skin and Silken Skin, from a joint process.…
A: Joint costs are those costs which are incurred simultaneously for production and manufacturing of…
Q: A manufactured product has the following information for June. Standard Quantity and Cost 6 pounds @…
A: Variance analysis is used for performance evaluation where the standard sets are compared with the…
Q: Crystal Pools estimates overhead will utilize 235,004 machine hours and cost $896,685. It takes 8…
A: Cost per unit: = Direct material + Direct labor + Overhead
Step by step
Solved in 2 steps
- Compute the standard cost for one pair of boots, based on the following standards for each pair of boots:Standard materials quantity: 1.25 yards of leather at $35.00 per yardStandard labor: 9 hours at $25.75 per hourFactory overhead: $1.76 per direct labor hourRound your answer to two decimal places.Total standard costCompute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 80 parts. A part requires 2 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy Value-added time min min Non-value-added time min min Total lead time min min Value-added ratio (as a percent) % 0%The following standard costs were developed for one of the products of ELJAY Sdn Bhd (ESB): STANDARD COST PER UNIT RM Direct materials Direct labor 3 feet @ RM4.00 per foot 5 hours @ RM8.00 per hour 5 hours @ RM4.00 per hour 5 hours @ RM6.00 per hour 12.00 40.00 Variable overhead Fixed overhead Total standard cost per unit 20.00 30.00 102.00 The following information is available regarding the company's operations for the period: Units produced Materials purchased Materials used Direct labor Overhead incurred: 40,000 240,000 feet at RM4.40 per foot 150,000 feet 220,000 hours at RM8.30 per hour Variable RM770,000 Fixed RM900,000 Budgeted fixed overhead for the period is RM960,000, and the standard fixed overhead rate is based on the expected capacity of 160,000 direct labor hours. REQUIRED: (a) Compute the following variances. Indicate whether it is Favorable (F) or Unfavorable (UF) variance. (i) material price variance
- Becton Labs, Incorporated, produces various chemical compounds for industrial use. One compound, called Fludex, has the following standard cost per unit: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 2.40 ounces $ 18.00 per ounce $ 43.20 Direct labor 0.70 hours $ 14.00 per hour 9.80 Variable manufacturing overhead 0.70 hours $ 3.00 per hour 2.10 Total standard cost per unit $ 55.10 During November, the following activity was recorded related to the production of Fludex: Materials purchased, 12,000 ounces at a cost of $198,000. There was no beginning inventory of materials; however, at the end of the month, 3,200 ounces of material remained in ending inventory. The company employs 20 lab technicians to work on the production of Fludex. During November, they each worked an average of 160 hours at an average pay rate of $12.00 per hour. Variable manufacturing overhead is assigned to Fludex on the basis of direct labor-hours.…Becton Labs, Incorporated, produces various chemical compounds for industrial use. One compound, called Fludex, is prepared using an elaborate distilling process. The company has developed standard costs for one unit of Fludex, as follows: Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit Standard Quantity or 2.50 Hours ounces 0.90 hours Standard Price or Rate $ 22.00 per ounce $ 16.00 per hour 0.90 hours $ 2.00 per hour Standard Cost $ 55.00 14.40 1.80 $ 71.20 During November, the following activity was recorded related to the production of Fludex: a. Materials purchased, 14,000 ounces at a cost of $289,800. b. There was no beginning inventory of materials; however, at the end of the month, 4,050 ounces of material remained in ending inventory. c. The company employs 26 lab technicians to work on the production of Fludex. During November, they each worked an average of 150 hours at an average pay rate of $15.00 per hour. d. Variable…Chenwang Manufacturing has 18,000 labor hours and 120,000 grams of material. The cost of labor per hour is $10, and material costs 60 cents per gram. The company manufactures three products: A, B and C. Quantity of material used per unit of each product, labor time used, demand, and selling price are given in the table below. Production has to equal or exceed demand. Image has been attached with the further details.
- Winner’s Circle, Inc., manufactures medals for winners of athletic events and other contests. Its manufacturing plant has the capacity to produce 10,000 medals each month. Current monthly production is 7,500 medals. The company normally charges $175 per medal. Variable costs and fixed costs for the current activity level of 75 percent of capacity are as follows: Production Costs Variable costs: Manufacturing: Direct labor………………………………………………….$ 375,000 Direct material………………………………………………….262,500 Marketing……………………………………………………………….187,500 Total variable costs……………………………………………………………$ 825,000 Fixed costs: Manufacturing………………………………………………………..$ 275,000 Marketing……………………………………………………………….175,000 Total fixed costs……………………………………………………………...$ 450,000 Total costs……………………………………………………………………$1,275,000 Variable cost per unit………………………………………………………..$ 110 Fixed cost per unit…………………………………………………………………….60 Average unit cost……………………………………………………………$ 170 Winner’s Circle has just received a…Oriole's standard quantities for 1 unit of product include 3 pounds of materials and 2.5 labor hours. The standard rates are $4 per pound and $5 per hour. The standard overhead rate is $8 per direct labor hour. The total standard cost per unit of Oriole's product isGerber Clothing Inc. has designed a rain suit for outdoor enthusiasts that is about to be introduced on the market. A standard cost card has been prepared for the new suit, as follows: Standard Quantity or hours Standard price or Rate Standard Direct materials 2.2 metres Direct labour 1.0 hours Manufacturing overhead (1/6 variable) 1.0 hours $ 15 per metre 33 per hour 21 per hour Cost $33.00 Total standard cost per suit 33.00 21.00 $87.00 a. The only variable selling and administrative costs will be $6 per suit for shipping. Fixed selling and administrative costs will be as follows (per year): Salaries Advertising and other Total $ 35,400 157,000 $192,400 b. Since the company manufactures many products, it is felt that no more than 10,500 hours of labour time per year can be devoted to production of the new suits. c. An investment of $550,000 will be necessary to carry inventories and accounts receivable and to purchase some new equipment. The company wants a 20% ROI in new product…
- Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 5 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 6 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy Value-added time ? min ? min Non-value-added time ? min ? min Total lead time ? min ? min Value-added ratio…LZS Bhd produces a single product called MY2.5 which is being exported to Indonesia. You are the management accountant of LZS Bhd and for the month ended 31 May 2021 you are provided with the following information in relation to MY2.5. (i) Standard cost per unit of MY2.5. Direct Materials : 4 kg per unit at RM3 per kg Direct Labour : 5 hours per unit at RM4 per hour Variable Overhead : 5 hours per unit at RM1 per hour Fixed Overhead : 5 hours per unit at RM3 per hour (ii) Standard selling price of MY2.5 is RM60 per unit. (iii) Budgeted production was 10,000 units . (iv) Overheads are absorbed based on the direct labour hours. (v) The actual results for the year are as follows: Sales at 9,500 units at a total sales of RM 551,000 Material consumption : 37,000kg of material at a total cost of RM120,250 Labour paid per hour : RM4.1 per hour to all factory workers. Labour cost paid in total : RM 200,900 Overheads paid : Variable : RM 46,550; Fixed : RM 145,000 (vi) No stocks held at the end…Jackson Fabricators Inc. machines metal partS TOI he dutomove mOusuryUnu e two processes: milling and finishing. Parts are produced in batch slzes of 60 parts, A part requires 3 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that Includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methads. If required, round percentages to one decimal place.