A small project consists of 3 activities P, Q and R to be executed in that sequence. The relationship between time duration (in 'Units of time -T) and corresponding total direct cost (C units) for each of the activities, for alternate mutually exclusive possible durations for each activity, are tabulated herewith: Q R 8. 250 340 8. 400 235 320 10 375 10 225 295 12 350 11 215 9. 275 For a total duration of 25 units of time, the least total direct cost for the complete project will be A965 units • B950 units C940 units D925 units 678 C.
A small project consists of 3 activities P, Q and R to be executed in that sequence. The relationship between time duration (in 'Units of time -T) and corresponding total direct cost (C units) for each of the activities, for alternate mutually exclusive possible durations for each activity, are tabulated herewith: Q R 8. 250 340 8. 400 235 320 10 375 10 225 295 12 350 11 215 9. 275 For a total duration of 25 units of time, the least total direct cost for the complete project will be A965 units • B950 units C940 units D925 units 678 C.
Related questions
Question
100%

Transcribed Image Text:A small project consists of 3 activities P, Q and R to be executed in that sequence.
The relationship between time duration (in 'Units of time -T) and corresponding
total direct cost (C units) for each of the activities, for alternate mutually exclusive
possible durations for each activity, are tabulated herewith:
Q
R.
T.
C
250
340
8.
400
235
320
10
375
10
225
8
295
12
350
11
215
6.
275
For a total duration of 25 units of time, the least total direct cost for the complete
project will be
A965 units
•8950 units
C940 units
D925 units