A small electrical appliance is to be produced on a single-model assembly line. The individual tasks of assembling the product are shown in Table 2. The table also lists the times for each task and the precedence order in which they must be performed. The line is to be balanced for an annual demand of 100,000 units/year. The line will operate 50 week/ year, 5 shifts/ week, and 7.5 hours/ shift. Table 2 Task Task Description Task Time Must be Preceded (min) By Place frame and clamp 0.2 2 Assemble plug, grommet to power cord 0.4 3 Assemble brackets to frame 0.7 4 Wire power cord to motor 0.4 1,2 5 Wire power cord to switch 0.3 2 6 Assemble mechanism plate to bracket 0.11 3 7 Assemble blade to bracket 0.32 3 8 Assemble motor to brackets 0.6 3,4 9 Align blade and attach to motor 0.27 6, 7, 8 10 Assemble switch to motor bracket 0.38 5,8 11 Attach cover, inspect, and test 0,5 9,10 12 Place in tote pan for packing 0.12 11
A small electrical appliance is to be produced on a single-model assembly line. The individual tasks of assembling the product are shown in Table 2. The table also lists the times for each task and the precedence order in which they must be performed. The line is to be balanced for an annual demand of 100,000 units/year. The line will operate 50 week/ year, 5 shifts/ week, and 7.5 hours/ shift. Table 2 Task Task Description Task Time Must be Preceded (min) By Place frame and clamp 0.2 2 Assemble plug, grommet to power cord 0.4 3 Assemble brackets to frame 0.7 4 Wire power cord to motor 0.4 1,2 5 Wire power cord to switch 0.3 2 6 Assemble mechanism plate to bracket 0.11 3 7 Assemble blade to bracket 0.32 3 8 Assemble motor to brackets 0.6 3,4 9 Align blade and attach to motor 0.27 6, 7, 8 10 Assemble switch to motor bracket 0.38 5,8 11 Attach cover, inspect, and test 0,5 9,10 12 Place in tote pan for packing 0.12 11
MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
Related questions
Question
i. Draw the precedence diagram.
ii. Calculate the cycle time and theoretical number of required workstations.
iii. Assign tasks to workstation using greatest positional weight rule.
iv. Determine the efficiency of your line balance.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Recommended textbooks for you
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman