A service has five tasks, performed in sequence. In the instance when there is more than one worker assigned to a task, each worker performs the entire task and they both can be working on different “items” at the same time. Task Task time per worker Number of workers 1 2 minutes 1 2 6 minutes 1 3 14 minutes 2 4 4 minutes 1 5 15 minutes 3 What is the capacity (hourly) of the process as a whole? What is the bottleneck of the process? What is the throughput time (assuming no wait time)? Where would you expect customers to wait?
Contingency Table
A contingency table can be defined as the visual representation of the relationship between two or more categorical variables that can be evaluated and registered. It is a categorical version of the scatterplot, which is used to investigate the linear relationship between two variables. A contingency table is indeed a type of frequency distribution table that displays two variables at the same time.
Binomial Distribution
Binomial is an algebraic expression of the sum or the difference of two terms. Before knowing about binomial distribution, we must know about the binomial theorem.
A service has five tasks, performed in sequence. In the instance when there is more than one worker assigned to a task, each worker performs the entire task and they both can be working on different “items” at the same time.
Task |
Task time per worker |
Number of workers |
1 |
2 minutes |
1 |
2 |
6 minutes |
1 |
3 |
14 minutes |
2 |
4 |
4 minutes |
1 |
5 |
15 minutes |
3 |
- What is the capacity (hourly) of the process as a whole?
- What is the bottleneck of the process?
- What is the throughput time (assuming no wait time)?
- Where would you expect customers to wait?