A proposed embankment fill requires 7500 m³ of compacted soil. The void ratio of the compacted fill is specified as 0.7. Soil can be transported from one of the four borrow pits, as described in the following table. The void ratio, specific gravity of soil solids, and the cost per cubic meter for moving the soil to the proposed construction site are provided in the table. a. Determine the volume of each borrow pit soil required to meet the spec- ification of the embankment site. b. Make the necessary calculations to select the borrow pit which would be most cost-effective. Borrow pit Void ratio GS Cost ($/m³) I 0.85 2.66 11 II 0.92 2.69 III 1.21 2.71 9 IV 0.89 2.73 10 Q
Q: 8-6 The open-ended polyvinyl chloride pipe has an inner diameter of 4 in. and thickness of 0.2 in.…
A: To determine the state of stress in the walls of the polyvinyl chloride (PVC) pipe, we can use the…
Q: Kindly solve this question under Measurement and Specifications for Civil Engineers.
A: Based on the information provided and the Contract Specifications, here's the takeoff for the…
Q: Wo 2x ВА Od
A: Here's a step-by-step approach:1. Identify Joints and Members:The truss has 6 joints (labeled A, B,…
Q: Common Forms of Carbon Research on the different forms of carbon stated below, take note of their…
A: Research on the different forms of carbon stated below, take note of their color, hardness,…
Q: In the figure below, find the elements of the Curve L= ? Z=? P.v.c g₁ = -3% 3+76 P.v.T? A P.V.I 3+51…
A: The previous response provided a good explanation for solving the problem of the missing elements (L…
Q: 3. An undisturbed sample of soil has a volume of 100 cm3 and mass of 190 g. On ovendrying for 24…
A: Step 1:Step 2:Step 3:
Q: a v-shaped channel, build of unplanned timber 0.080 m/ with a velocity of 2.5 m/s. each of the sides…
A:
Q: A brick lined trapezoidal canal has side slopes of 1.5 horizontal to 1 vertical. It is required to…
A:
Q: 8
A: Step 1:Given:D = 1.25 ind = 1 in Speed of the shaft = 2250 rpm. Allowable shearing stress: 7500 psi.…
Q: Wo 2x ВА Od
A: Step 1:Step 2:Step 3:Step 4:Hope this helps!
Q: Determine the resultant reactions at each support of the structure. Indicate the direction of…
A: 1. Summation moment at B:Reaction at A = 200.11 KN Summation Forces Along y-axis:Reaction By = 92.70…
Q: Analyze the propped beam loaded as shown below: 12 kN/m A 4 m B 4 m a) Determine the reaction at the…
A: Step 1:Step 2:Step 3: Step 4:
Q: Situation 3. A W12x81 is used as a column. The effective length in either principal direction is…
A: The question asks you to find the cutback width (labeled as 2.187) based on the given information.…
Q: 11.10 A concrete pile 0.406 m x 0.406 m in cross section is shown in Figure P11.10. Calculate the…
A:
Q: a) What is a load factor? b) How would you determine the load factor for a structure?
A: Step 1: Step 2: Step 3: Step 4:
Q: The formation of a valley has a hydraulic conductivity of 400 ft/day and porosity of 0.25. The water…
A: In a valley situation, where groundwater flow parameters are impacted by hydraulic conductivity,…
Q: Problem 5. For the beam shown in the figure, determine a) slope at B, b) the reactions at the…
A: Step 1:Step 2:Step 3:Step 4:
Q: The potassium industry is perfectly competitive. Firms act as price takers and each firm in the…
A: To provide a detailed explanation of the answers, we will break down each step and provide relevant…
Q: a drainage canal having a trapezoidal shape has a base equal to 2 meters and the depth of water is 1…
A: Step 1:The hydraulic radius is a concept used in hydraulic engineering to represent the effective…
Q: 2 Find the relation error use the Trapezoid rule to approximate the definite integral. use n=4, S Po…
A: To find the approximation error using the Trapezoid Rule, we first need to compute the actual value…
Q: P12.42 Mohr's circle is shown for a point in a physical object that is subjected to plane stress.…
A: Approach to solving the question: Detailed explanation: Examples: Key references:
Q: The simple beam 120mm x 420 mm cross section has E= 9.50 GPA Determme the vertical movement of point…
A:
Q: 114 A driven closed-ended pile, circular in cross section, is shown in Figure P11.4. Calculate the…
A:
Q: please answer hydrology question. make sure it is correct. will thumbs up if correct.
A: Step 1: Calculate the critical depth The critical depth is denoted by ;…
Q: combined gas law
A:
Q: 5KN 15KN DX Im лиш Х * Figure 6a Assume that the beam in Figure 6a has the cross-section shown in…
A: Step 1:Step 2: Step 3: Step 4:
Q: Current Attempt in Progress A lost shipping container is found resting on the ocean floor and…
A: Step 1:Volume of the container is 6.3m long,2.8m wide,2.8m highRadius of the balloon is1.5mDensity…
Q: (2) A force P holds a string tightly stretched in the position shown. Determine the motion of the…
A: Sure, The motion of the string after the force is removed. As mentioned previously, we can tackle…
Q: The beam shown in the figure below (Figure 1) is made of steel that has an allowable stress of…
A: Step 1: Step 2:Note- In moment of inertia formula "b" is dimension parallel to the axis and "h" is…
Q: *84 The thin-walled cylinder can be supported in one of two ways as shown. Determine the state of…
A: Step 1: Step 2: Step 3: Step 4:
Q: In the sport of curling, athletes slide stones with a mass of about 20 kg across a level ice surface…
A: Please see the attached images for the solution. If there are queries, please do not hesitate to…
Q: I need isometric of the shape
A: The information provided in the question image is not enough to solve the problem.To draw isometric…
Q: Determine the resultant reactions at each support of the structure. Indicate the direction of…
A:
Q: 6-50 The beam is subjected to a moment of M = 40 kN. m. Determine the bending stress acting at…
A: ANSWER :
Q: A channel has been designed to convey clear water to a fish hatchery. The design calls for aflow…
A: The objective of the question is to determine if the existing design of the channel is adequate to…
Q: For the cashflow diagram below, what is the equivalent annual worth? Consider i=8%. 0 1 2 3 4 5 6…
A: 1. Calculate the Present Value (PV) of each cash flow using the formula:PV=(1+i)nFVwhere ( FV ) is…
Q: Derive the labor and equipment cost for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture…
A: Step 1: Compute the total desired output in cubic meters by multiplying the wall area by its…
Q: A glass windowpane in a home is 0.62 cm thick and has dimensions of 1.4 m x 1.9 m. On a certain day,…
A:
Q: Analyze the cantilever beam loaded as shown below: 10 kN A 6 m 2 kN/m 0 B 4 m a) Determine the…
A: Step 1:Step 2:Step 3:
Q: A swimming pool with vertical sides is 25m king and 10m wide. Water at the feel and shallow ends is…
A: Step 1: To solve these problems, we'll need to apply principles of fluid dynamics and use relevant…
Q: Please do not rely too much on chatgpt, because its answer may be wrong. Please consider it…
A: Ans(a) Step 1:Given α=45oNow draw the FBD of the given figure as Step 2: Now take equilibrium in x…
Q: Please solve the problem in the picture
A: Step 1:
Q: A Contract for an office building includes the provision of a storage tank. Drawing No Q₁ shows the…
A: However, as mentioned earlier, I can't perform a complete structural analysis based solely on an…
Q: 5. a. Discuss, Green engineering design as function of Population Growth? b. The population was 9.98…
A: Green engineering design refers to the use of techniques and procedures that can reduce…
Q: Q2: A highway of 50 km length, it is required to be paved 8 cm wearing course layer. 12 m width.…
A:
Q: A 20 kg box is placed on an incline plane against a stop as shown below. A flexible cable is…
A: Step 1:Step 2:Step 3:Step 4:
Q: Suppose we have a uniform beam that is 3.40metres long has a flexural rigidity of 31915N Find the…
A:
Q: The simple beam 120mm x 420 mm cross section has E= 9.50 GPA Determine the vertical movement of…
A: Reactions: Shear Diagram: Bending Moment Diagram:
Q: Question 1 If the waste with BOD4-30 equal 150 mg/l and K1-20 0.23/day is discharge to a stream At…
A: Step 1:Step 2:Step 3:Step 4:
Q: DUE NOW. Please answer immediately please.
A: Estimating Rainfall for Station K in July 83There are two commonplace methods used to estimate…
Step by step
Solved in 2 steps
- A proposed embankment fill requires 7500 m3 of compacted soil. The void ratio of thecompacted fill is specified as 0.7. Soil can be transported from one of the four borrowpits, as described in the following table. The void ratio, specific gravity of soil solids,and the cost per cubic meter for moving the soil to the proposed construction site areprovided in the table.a. Determine the volume of each borrow pit soil required to meet the specification ofthe embankment site.b. Make the necessary calculations to select the borrow pit which would be most costeffective.Problem 3: A proposed embankment fill requires 7500 m³ of compacted soil. The void ratio of the compacted fill is specified as 0.7. Soil can be transported from one of the four borrow pits, as described in the following table. The void ratio, specific gravity of soil solids, and the cost per cubic meter for moving the soil to the proposed construction site are provided in the table. a. Determine the volume of each borrow pit soil required to meet the specification of the embankment site. b. Make the necessary calculations to select the borrow pit which would be most cost-effective. Borrow pit Void ratio G, Cost ($/m³) I 0.85 2.66 11 II 0.92 2.69 8 III 1.21 2.71 9. IV 0.89 2.73 1030. The proposed embankment fill requires 8000m³of compacted soil. The void ratio of the compacted fill is specified as 0.70. Four borrow pits are available as described in the following table, which list the respective void ratios of the soil and the cost per cubic meter for moving the soil to the proposed construction site. Assume that the specific gravity is the same at all pits, which among the pits should be bought to minimize the cost? Borrow Pit Void Ratio Cost (P/m³) A 0.82 400 B 0.9 450 1.1 250 D 0.78 600
- Problem 11. The proposed embankment fill requires 8000m of compacted soil. The void ratio of the compacted fill is specified as 0.70. Four borrow pits are available as described in the following table, which list the respective void ratios of the soil and the cost per cubic meter for moving the soil to the proposed construction site. Assume that the specific gravity is the same at all pits, which among the pits should be bought to minimize the cost? Void Ratio Cost (P/m3) Borrow Pit A 0.82 400 0.9 450 1.1 250 D 0.78 600Standard proctor compaction test results on a sandy clay (35% sand, 55% clay, and 10% silt), taken from a borrow pit, are given in the following table. The sandy clay in the borrow pit has a porosity of 65% and a water content of 5.2%. A highway embankment is to be constructed using this soil. (a) Specify the compaction (dry unit weight and water content) to be achieved in the field. Justify your specification. (b) How many cubic meters of borrow pit soil are needed for 1 cubic meter of highway fill? (c) How much water per unit volume is required to meet the specification? (d) How many truckloads of soil will be required for a 100,000 m3 highway embankment? Each truck has a load capacity of 22.5 m3 and regulations required a maximum load capacity of 90%. (e) Determine the cost for 100,000 m3 of compacted soil based on the following: Purchase and load borrow pit material at site, haul 2 km round-trip, and spread with 200 HP dozer = $15/m3; extra mileage charge for each km =…A proposed embankment fill requires 8000 ?3 of compacted soil. The void ratio of the compacted fill is specified as 0.70. Four borrow pits are available as described in the table which list the respective void ratios of the soil and cost per cubic meter for moving the soil to the proposed construction site. Make necessary calculations to select pit from which the soils should be bought to minimize the cost. Assume specific gravity to be the same at all pits.
- The sieve analysis data for a granular soil are given below. • % passing 76.2 mm sieve = 98 • % passing 4.75 mm sieve = 63 • % passing 0.075 mm sieve = 16 What would be the percentage of gravel by the AASHTO classification system? Answer:Your company has won a contract to provide and compact the fill material for an earth levee (an embankment built to prevent overflow of a river), with the dimensions shown below. The levee fill is a silty clay soil to be compacted to atleast 95.1% of maximum standard Proctor of dry unit weight= 109lb/cu.ft at an OMC of 18.6%. Your borrow pit has a silty clay with an in-situ moist density of 112.6lb/cu.ft at 18.1% water content and a Gs = 2.679. When the soil is excavated and loaded on to your trucks, the void ratio of the material is e = 1.46. Your trucks can haul 401 cu.ft of material per trip. DETERMINE THE FF AND SHOW COMPELETE SOLUTION. ALL FINAL ANSWER WILL BE IN 3 DECIMAL PLACES. 1. Determine the volume of fill required for the levee in cu.ft 2. Determine the volume required from the borrow pit in cu.ft 3. Determine the required number of truck loads.A proposed earth embankment requires 60,000 cubic meters of soil. The soil will be compacted to a void ratio of 0.85. Two borrow pits designated as A and B are available near the site. The void ratio of the soil in each pit and the estimated cost per cubic meter for moving the soil to the site are as shown below. Pit Void Ratio Cost ($/m3) A 1.10 5.00 B 1.80 3.70 Which will have the lowest cost to move and be the most economical to use?
- Read the question carefully and give me both a&b right solutions. A proctor compaction test in the laboratory on a borrow pit soil gives maximum unit weight of 19 kN/m3 and optimum water content of 11.5%. The bulk unit weight and water content of the soil in the borrow pit are 17.2 kN/m3 and 8.2%, respectively. A highway fill is to be constructed using this soil. The specifications require the fill to be compacted to 95% Proctor compaction. (a) What is the additional weight of water per unit volume required to bring the moisture content to the optimum value to achieve 95% Proctor compaction? (b) How many truckloads of borrow pit soil will be required for a 100,000 m3 highway embankment - assuming each truck has a capacity of 10 m3 ?1. Why will bulk density vary between soils but it is valid to use a constant value for particle density (2.65 g cm-3)?Suppose that you are a Project Engineer on a Dam project. The volume of soil required at the dame site is Vd=100,000m3. The final void ratio (ed) is 0.80. Your boss, the Project Manager delegates to you the important decision of buying the earth fill from one of three suppliers. • Supplier X sells fill at OMR. 0.200/m3 with e = 0.90• Supplier Y sells fill at OMR. 0.120/m3 with e = 2.00• Supplier Z sells fill at OMR. 0.150/m3 with e = 1.60Evaluate and select the best supplier based on your knowledge about soil compaction.