A project's internal rate of return (IRR) is the  that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the  on a bond. The equation for calculating the IRR is:     CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal . The IRR calculation assumes that cash flows are reinvested at the . If the IRR is  than the project's risk-adjusted cost of capital, then the project should be accepted; however, if the IRR is less than the project's risk-adjusted cost of capital, then the project should be . Because of the IRR reinvestment rate assumption, when  projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR:  differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the  method should be used to evaluate projects. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%.     0 1 2 3 4                       Project A -1,050 600 360 300 290 Project B -1,050 200 295 450 740   What is Project A’s IRR? Do not round intermediate calculations. Round your answer to two decimal places.  % What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.  % If the projects were independent, which project(s) would be accepted according to the IRR method?   If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?   Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?   The reason is  Reinvestment at the  is the superior assumption, so when mutually exclusive projects are evaluated the  approach should be used for the capital budgeting decision.

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
Question

A project's internal rate of return (IRR) is the  that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the  on a bond. The equation for calculating the IRR is:

 

 

CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal .

The IRR calculation assumes that cash flows are reinvested at the . If the IRR is  than the project's risk-adjusted cost of capital, then the project should be accepted; however, if the IRR is less than the project's risk-adjusted cost of capital, then the project should be . Because of the IRR reinvestment rate assumption, when  projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR:  differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the  method should be used to evaluate projects.

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%.

 

  0 1 2 3 4
                     
Project A -1,050 600 360 300 290
Project B -1,050 200 295 450 740

 

What is Project A’s IRR? Do not round intermediate calculations. Round your answer to two decimal places.

 %

What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.

 %

If the projects were independent, which project(s) would be accepted according to the IRR method?

 

If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?

 

Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?

 

The reason is 

Reinvestment at the  is the superior assumption, so when mutually exclusive projects are evaluated the  approach should be used for the capital budgeting decision.

 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education