A project with the following activities is given. The direct cost of the project is "C" and the indirect cost of the project is $5 per day. If you crash a schedule, you add to project's direct cost (e.g., if you crash activitiy B for 1 day then the total direct cost would be C + $2) but save on project's indirect costs ($5 per day) by paying less due to a crashed schedule which is shorter than the original one. You are being asked to reduce project duration to 19 days in the most economical way. In your answers explain: 1. the steps that you would take to do so and why 2. total direct cost of the project
A project with the following activities is given. The direct cost of the project is "C" and the indirect cost of the project is $5 per day. If you crash a schedule, you add to project's direct cost (e.g., if you crash activitiy B for 1 day then the total direct cost would be C + $2) but save on project's indirect costs ($5 per day) by paying less due to a crashed schedule which is shorter than the original one. You are being asked to reduce project duration to 19 days in the most economical way. In your answers explain: 1. the steps that you would take to do so and why 2. total direct cost of the project
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![A project with the following activities is given. The direct cost of the project is "C" and the indirect cost of the project is $5 per day. If you crash a schedule, you add
to project's direct cost (e.g., if you crash activitiy B for 1 day then the total direct cost would be C + $2) but save on project's indirect costs ($5 per day) by paying
less due to a crashed schedule which is shorter than the original one. You are being asked to reduce project duration to 19 days in the most economical way. In
your answers explain:
1. the steps that you would take to do so and why
2. total direct cost of the project
Activity
Preceding Activity
Normal Time (day)
Crash Time (day)
Cost Slope
A
2
2
3
В
4
2
2
C
A
3
2
3
D
А, В
6.
1
E
7
4
4
C
3
G
4
2
3
H
D, E
5
4
5
F, G
I, G
3
4
6.
1
K
2
2](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ffdbb3914-d1f1-4547-8cab-f1cdf0ee63f7%2Fb159b2c6-0269-43ce-947d-2391754d3274%2F58r863c_processed.png&w=3840&q=75)
Transcribed Image Text:A project with the following activities is given. The direct cost of the project is "C" and the indirect cost of the project is $5 per day. If you crash a schedule, you add
to project's direct cost (e.g., if you crash activitiy B for 1 day then the total direct cost would be C + $2) but save on project's indirect costs ($5 per day) by paying
less due to a crashed schedule which is shorter than the original one. You are being asked to reduce project duration to 19 days in the most economical way. In
your answers explain:
1. the steps that you would take to do so and why
2. total direct cost of the project
Activity
Preceding Activity
Normal Time (day)
Crash Time (day)
Cost Slope
A
2
2
3
В
4
2
2
C
A
3
2
3
D
А, В
6.
1
E
7
4
4
C
3
G
4
2
3
H
D, E
5
4
5
F, G
I, G
3
4
6.
1
K
2
2
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning